DocketNumber: No. 09-857C
Citation Numbers: 93 Fed. Cl. 416, 2010 WL 1976825
Judges: Allegra
Filed Date: 5/13/2010
Status: Precedential
Modified Date: 10/18/2024
OPINION
This post-award bid protest case is before the court on the parties’ cross-motions for judgment on the administrative record. Plaintiff, Electronic Data Systems, LLC (EDS), protests the Department of Treasury’s award of a contract to BAE Systems Information Technology, Inc. (BAE) to provide information technology infrastructure support services. For the reasons that follow, the court DENIES plaintiffs motion for judgment on the administrative record and GRANTS defendant’s and defendant-interve-nor’s cross-motions.
I. BACKGROUND
The administrative record in this case reveals the following:
On September 6, 2008, Treasury issued Request for Proposals (RFP) #A08-047, seeking a contractor to provide a “reliable, secure, efficient, effective, and technologically current IT infrastructure” to support the agency’s ongoing efforts — a bundle of services the RFP denoted as “Information Technology Infrastructure Managed Services” or “IT IMS.” It contemplated the award of an infinite delivery/infinite quantity, performance-based service contract with a base period of three years and two successive two-year award terms, which the awardee could earn through outstanding performance. Individual task orders placed under the proposed contract were to be issued on a time- and-materials, or fixed-price basis (or a combination thereof). The ceiling for the contract is $325 million, with a guaranteed minimum of $250,000. The RFP provided that the award of the contract would be on a negotiated, “best value” basis.
A. The RFP
1. Proposal Requirements
The RFP’s requirements took the form, in part, of several Contract Line Items (CLINs). Three of these — CLINS 002, 003 and 004 — were denominated “core services,” with portions of each related to end user services, data center operation and local area network (LAN) operations, and disaster recovery and continuity of operations. End user services were sought to provide Treasury employees with “the technology and infrastructure required to perform their job functions,” including desktop computers and software for all users, and laptops and personal device assistants (PDAs) for specified users, as well as technological support, including both remote and desk side assistance. The infrastructure services desired involved the development and maintenance of data center operations and network systems, including “major hardware and infrastructure software platforms,” such as “network router, switch, hub, and concentrator devices.” Finally, the solicitation emphasized
Offerors were to propose fixed prices for each of these core services based on a population of 2,100 Treasury end users (later increased to 2,700 users). To define the needs of these employees, the RFP sketched Treasury’s current standard configurations in various ways — indicating, for example, the types of work stations to be employed; the base standards for end user’s hardware and software; and the number of service installs, moves, calls, etc., that had been made over the past five fiscal years. The RFP required each offeror to propose a user base expansion price (UBE) to support up to 200 additional end users should the need arise. The proposed UBE price was to be a fixed monthly charge, per user, which would be added to the base monthly fixed price of the core services CLINs if and when additional users were added.
Two other CLINs are relevant here. CLIN 005 required the contractor to maintain an online catalog of hardware and software which Treasury could use to acquire additional items beyond those included in the core services package. Offerors were to propose pricing for the on-line catalog at a fixed discount off the “lowest publicly available price,” as determined by the General Services Administration federal supply schedule or other government-wide contract vehicles. While software prices in the catalog had to be updated only annually, the cost of hardware, handheld devices, peripherals and network and data center equipment had to be updated every six months.
CLIN 006 required offerors to delineate a technical approach and pricing for a sample task project (the Sample Task) designed to be representative of the tasks Treasury might order during the course of the contract. The Sample Task involved supporting a hypothetical new Treasury office with 100 employees for three months. The RFP mapped out the following more detailed requirements:
Local
• 100 Workstations (laptops) for the 100 person staff with standard configurations.
• 20 Blackberry devices.
• 1 color and 1 black and white printer for every 15 people.
• Network switches and patching, as required.
• Local print server.
Data Center
• 1 — Oracle server to support the 100 person staff and a Commercial Off the Shelf (COTS) application to provide at least 500 GB data storage.
• Oracle licenses will be required for each of the 100 people.
• 1 — IIS server so that the application may be web enabled.
• Secure remote access facilities as provided to all Treasury DO [Departmental Offices] users.
• Access to all other Treasury DO applications.
Firewall
• A firewall in the DO Data Center must be purchased and configured that limits access from Public Debt to the DO LAN.
• The firewall must allow only the 100 authorized TEMP users to access Public Debt.
Regarding pricing, the RFP indicated that “[t]he Labor Rates and the on-line catalog established in the contract will be used to build the Task Order (TO) pricing,” but that “[o]fferors shall provide a price that supports their approach ... for this Sample Task as an IDIQ proposal with labor rates, and hardware and software charges.” The prices of specific items were to be reflected on a worksheet that was provided with the RFP.
The RFP’s performance work statement (PWS) further refined Treasury’s objectives using Service Level Agreements (SLAs) that established service level metrics and acceptable quality levels (AQLs) for particular work. Regarding these measures, the RFP explained—
The IT IMS Contract shall have defined Performance Standards and AQLs for core and supporting service areas established through SLAs. The “Performance Target” defines the desired value or best case scenario for a particular metric within a service area, while the AQL defines the minimum acceptable performance level or worst case scenario which is still considered acceptable for that metric, below*422 which the Contractor will be found “deficient” in performance.
The RFP went on to explain that “[w]hen the Contractor’s measured performance on a particular metric is below the AQL value, the Government may assess a disincentive,” adding that “not meeting the AQL in one metric in the service area will render the contractor’s performance as deficient for the entire service area.” Offerors were instructed that their proposals should include a “[djescription of the Offeror’s approach to ensuring how they will meet the performance metrics.”
Particularly relevant herein are the SLA standards for certain data center functions, which were outlined in section 4.2 of the PWS. This segment of the RFP defined data center operations as “the centralized support of information technology equipment, resources and the underlying physical infrastructure along with the processes and organizational structure required to establish an IT operating environment.” Inter alia, the SLAs set performance targets of 99.99 percent availability, not including scheduled downtime, for the data center’s e-mail function, file and printing functions, and application transport. Each of these SLAs had an AQL of “no deviation.”
2. Evaluation Criteria
The award was to be made to the offeror whose proposal was determined to be most beneficial to the government, with appropriate consideration given to four evaluation factors, listed in descending order of importance: Managed Services Solution, Performance Risk, Price and Small Business Participation. The RFP indicated that, when combined, the non-price factors — Managed Services Solution, Performance Risk and Small Business Participation — were significantly more important than Price.
Each proposal’s technical approach was to be evaluated according to the extent it ensured attainment of program objectives, and the probability that it would succeed in achieving the contract goals. Toward that end, each sub-factor and factor evaluated was to be assigned one of five adjectival ratings (outstanding, good, acceptable, marginal, or unacceptable) based on the strengths/significant strengths, weaknesses/signifieant weaknesses, and deficiencies within each category.
The RFP required offerors to submit a pricing workbook that Treasury would use to compute the total evaluated price of each proposal. The total evaluated price consisted primarily of costs associated with the rele
In the RFP, Treasury reserved the right to conduct discussions with offerors in the competitive range. Offerors in that range were to be invited to make oral presentations to explain their written technical proposals, as well as their qualifications to perform successfully under the contract. Prior to the receipt of proposals, Treasury amended the solicitation on seven occasions — the last of which occurred on November 20, 2008.
B. Proposals and the Evaluation Process
On November 26, 2008, seven offerors submitted proposals in response to the RFP. On February 2, 2009, Treasury issued its initial price evaluation report on the proposals. The price evaluation report reviewed each offeror’s total price to determine whether it was fair and reasonable. EDS’ total evaluated price was $[ ], BAE’s was $[ ], and [a third offeror’s] was $[]. Both EDS’ and BAE’s total evaluated prices were determined to be reasonable, while the report noted that [the third offeror]’s price was “too high” compared to the other offerors’ prices. Accounting for the latter observation, the report found that [the third offeror’s] labor rates were [] percent higher than the average calculation of all competitors’ rates.
The price evaluation report also identified and compared each bid’s individual CLIN pricing. As to the core services, the report found that the prices on two of EDS’ disaster recovery CLINs were “too high” when compared to the other proposals. However, it stated that “EDS’ ... overall CLIN prices were fair and reasonable.” With respect to CLIN 005, the on-line catalog, BAE and [the third offeror] proposed [] and []-percent discounts, respectively, off the lowest publicly available price, while EDS proposed [] discount. Treasury deemed EDS’ catalog pricing “fair and reasonable,” and, despite BAE’s and [the third offeror]’s discount, considered the difference in catalog prices between the bidders “immaterial.”
With respect to CLIN 006, the report found all three offerors’ proposals to be “incomplete.” [The third offeror] had excluded the cost of firewalls from its CLIN 006 pricing, while EDS had excluded six required color printers. The Treasury team found BAE’s hardware and software pricing to be significantly lower than that of both EDS and [the third offeror], and expressed concern that BAE was missing required items. While EDS’ and [the third offeror]’s hardware and software costs were $[] and $[], respectively, BAE’s costs were only $[ ]. The report found that this pricing differential occurred because “BAE’s sample task did not include pricing for any personal computers, blackberrys or firewalls,” and thus “did not adequately price all hardwai’e and software items.” Regarding such costs, BAE’s acquisition plan stated—
BAE Managed Services will provide all equipment required to outfit the 100 new users for TEMP [the temporary Treasury office] to include the laptops, laptop accessories, monitors, Blackberries, network printers, network switches, servers, and associated software for the standard manage service user. This equipment is covered in our e-catalog as part of our 1-100 user upgrade. The equipment that falls outside of our normal user service, firewalls, Oracle client licenses, and 500 GB*424 SAN space, will be priced and provided in our proposal. These items are not normal use items for a managed services user and are therefore extra to that service.
BAE’s acquisition plan included a table that broke out the specific products to be acquired between those “Included in Managed Services” and those “Outside Managed Services.” This table described the products to be purchased with great specificity, e.g., “a Dell Latitude E5400 Laptop.” The items listed as “Included in Managed Services” were not listed in BAE’s Sample Task Pricing Chart; only two of the table items listed as “Outside Managed Services” were included in the Pricing Chart. BAE received a rating of “acceptable” for its Sample Task.
Contrasting the offerors’ UBE prices, Treasury again uncovered a discrepancy in the proposals: while BAE’s and [the third offeror’]s UBE prices were comparable, at $[ ] and $[ ], respectively, EDS’ was only $[ ]. This differential arose from the offerors’ different approaches to UBE pricing. While BAE included in its UBE price the same services and hardware and software costs it had included in its core services for base users, EDS included only the labor and other direct costs associated with adding an additional user, but not the associated hardware and software costs. EDS’ plan contemplated that Treasury would order such hardware and software directly from EDS’ on-line catalog, which EDS believed would create more transparency and flexibility than a fully-bundled UBE price.
On February 5, 2009, Treasury issued its initial technical evaluation report on all the offers, in which EDS, BAE, and [the third offeror] all received “good” overall ratings. With respect to BAE’s technical approach, the report commented that Treasury needed clarification regarding “the reliability tier level for the Herndon Data Center Facility as it relates to the standards defined by the Uptime Institute.”
Following this initial evaluation, on March 25, 2009, a competitive range was established consisting of EDS, BAE, and [the third offer- or], On April 7, 2009, Treasury notified BAE, EDS, and [the third offeror] that their offers were in the competitive range and that discussions would be necessary. In the ensuing discussions, Treasury informed all three offerors that the pricing for their CLIN 006 responses was incomplete. In addition, Treasury notified [the third offeror] that its total price and its proposed labor rates were too high. Treasury did not notify EDS that its disaster recovery CLINs were considered too high. The oral presentations envisioned by the RFP were made on April 20-22, 2009. On March 10, 2009, Treasury amended the RFP, requiring, inter alia, that final proposal revisions be submitted on May 12, 2009.
On May 12, 2009, BAE, EDS, and [the third offeror] submitted their final revised proposals. In its final bid, EDS increased its CLIN 006 hardware and software pricing to $[ ], to account for the six printers missing from its initial bid. BAE minimally increased its CLIN 006 hardware and software pricing to $[ ], but continued to exclude the bulk of its hardware and software costs from its Sample Task pricing. In its response to Treasury’s discussion questions, BAE clarified that the hardware and software costs it had excluded from its Sample Task price were included in its UBE price, which established a flat rate for “all managed services associated equipment and software,” including almost all of the hardware and software required for the Sample Task. BAE stated that any hardware or software not included in the UBE package was priced out in the Sample Task worksheet, stating that — “[t]he additional 500GB of Storage Area Network (SAN) space, firewalls, and Oracle client licenses are not part of the bundled managed services offering, therefore we will order them separately through the e-catalog, and priced them separately in the Sample Task
In its response to the discussion questions, which was submitted with its final proposal, BAE clarified that “[t]he Herndon Data Center Facility is a Tier II data center as defined by the Uptime Institute ... [and] is designed to meet 100% of Treasury’s specified data center requirement.” Elsewhere in its final proposal, BAE assured Treasury of its “expected performance in meeting and/or exceeding the identified SLA targets for all CLINS.” To back up this assertion, BAE described, in detail, its plans to meet the 99.99-percent availability targets by employing, for example: (i) a “clustered Exchange environment” to meet Treasury’s e-mail needs; (ii) a “clustered ... server configuration” to provide the requisite file and printing capability; and (iii) a solution with “high performance blade server environment and Netcool monitoring” to provide for application transport.
Following submission of the final proposals, Treasury issued final technical and pricing evaluation reports on the remaining of-ferors. Notwithstanding BAE’s assurances, Treasury’s technical evaluators remained concerned regarding the data center’s availability and reliability. Treasury assigned BAE a “significant weakness” for its data center, noting that—
A Tier II Data Center has an end-user availability of 99.75% (22 hours of downtime per year) ... This availability rating does not meet the availability/ reliability needed to support the IT IMS SLAs. The IT IMS SLA threshold is set at a minimum of 99.99% availability. Thus, use of the Herndon Data Center Facility could result in the Offeror failing to meet the metric specified in the SLA, thereby potentially incurring disincentives.
However, the evaluation team believed that this significant weakness was offset by two significant strengths and numerous other strengths in BAE’s technical proposal. This led them to conclude that “there is a high probability of success in each of the service areas” and, overall, that BAE’s technical solution presented a “strong probability of successful execution with a low degree of risk.” BAE’s technical approach sub-factor ultimately received an overall rating of “good.”
The price evaluation team found EDS’s final overall price to be “fair and reasonable,” while BAE’s was considered “substantially lower.” The team determined that “the Government has no basis to question [BAE’s substantially lower prices] with the exception of CLIN 006.” As to the latter point, the team acknowledged that “the three offerors did not utilize a common basis in developing their proposed HW/SW costs,” adding that
Following this analysis, the final evaluation results were as follows:
FACTOR/SUB-FACTOR MERIT RATING & PRICE
BAE $169,655,418
Overall Non-Price Rating Good
A. Managed Services Solutions Good
1. Technical Approach Good
2. Management Plan Good
3. Key Personnel Good
4. Sample Task Response Acceptable
B. Performance Risk Good
1. Past Performance Good
2. Corporate Experience Outstanding
C. Small Business Good
EDS $218,780,547
Overall Non-Price Rating A. Managed Services Solutions Good Good
1. Technical Approach Good
2. Management Plan Good
3. Key Personnel Acceptable
4. Sample Task Response Acceptable
B. Performance Risk Good
1. Past Performance Good
2. Corporate Experience Outstanding
C. Small Business Outstanding
[The Third Offeror] $[]
Overall Non-Price Rating Acceptable
A. Managed Services Solutions Acceptable
1. Technical Approach Acceptable
2. Management Plan Good
Key Personnel Good
4. Sample Task Response Acceptable
B. Performance Risk Good
1. Past Performance Acceptable
2. Corporate Experience Outstanding
C. Small Business Good
On July 8, 2009, the Source Selection Authority (SSA) issued his decision awarding the contract to BAE. In his decision, the SSA discussed the fact that BAE’s data center was a Tier II facility, stating—
*427 A Tier II Data Center has an end-user availability of 99.75% (22 hours of downtime per year). Although the IT IMS RFP did not specify a required availability percentage applicable directly to the data center, this availability percentage is lower than the availability threshold of the IT IMS SLAs which are 99.99%. Thus, use of a Tier II Facility potentially could result in the Offeror failing to meet the SLA metrics, thereby incurring disincentives. While this aspect of BAE’s proposal raises some concern, I note that BAE did in fact specify in their proposal response that they are able to meet the SLA availability requirements of 99.99% with their proposed solution. This may mean that BAE has not officially certified their facility under the requirements of the Uptime Institute, but does have (or will obtain) the physical infrastructure and capacity to meet the requirements of the SLAs.
The SSA cited various other “significant strengths” and “strengths,” including several associated with the data center, that supported, in his view, BAE’s rating of “Good” for the Technical Approach subfactor.
In addition, the SSA discussed the disparate approaches to hardware and software pricing taken by the offerors in CLIN 006, as follows:
The price analysis noted an issue with regard to the pricing of CLIN 006, the sample task. Specifically, there was a significant disparity in the HW/SW costs proposed by the three offerors. The HW/SW costs for CLIN 006 ranged from a low of $[ ](BAE) to a high of $[ ](EDS). According to the price analysis, it appears the three offerors did not utilize a common basis in developing their proposed HW/SW costs. In particular, BAE indicated that much of its HW/SW costs would be included in its “user base expansion” prices, and therefore would be excluded from its sample task price. Meanwhile, [the third of-feror] and EDS included costs for similar items in their sample task solutions.
For purposes of conducting my tradeoff analysis, I have attempted to determine what the offerors prices would have been if EDS and [the third offeror] had proposed HW/SW costs for CLIN 006 on the same basis as BAE. BAE’s price would be unchanged ($169,655,418). For EDS and [the third offeror], I cannot determine exactly what the prices would have been using the BAE approach. However, using the approach most favorable to EDS and [the third offeror], I have excluded CLIN 006 HW/SW costs for [the third offeror] and EDS altogether.
The SSA noted that with the adjustments he made, the offeror’s prices would be as follows:
CLIN Adjusted Offeror Total Price 006 HW/SW Price
BAE_$169,655,418 iff]_$11
EDS_$218,780,547 $[ J_$[]
[Third Offeror] $[]$[]$[]
The SSA noted that “even if HW/SW costs for CLIN 006 are excluded altogether for EDS and [the third offeror], BAE is still much lower in price than the other two offer-ors.”
In conducting his best value analysis, the SSA observed that while both EDS and BAE had received overall non-price ratings of “good,” “BAE has a lower price.” He noted that, without the adjustment associated with CLIN 006, BAE’s price was “substantially lower than EDS, by more than $49 million,” and found that BAE’s proposal was thus “superior” to EDS’. The SSA indicated that he still felt that BAE’s proposal was superior to that of EDS even if the CLIN 006 adjustments were made, stating that “even if HW/SW costs for CLIN 006 were excluded for EDS altogether, BAE would still enjoy a price advantage of more then $[ ] million over EDS.” Based on this analysis, the SSA concluded that BAE’s proposal represented the “best value” to the government, and, on that basis, awarded the contract to BAE. BAE began performing the IT IMS contract in July of 2009.
C. Procedural History
On July 30, 2009, EDS filed a bid protest before the Government Accountability Office (GAO). On September 10, 2009, EDS filed a supplemental protest with GAO. On November 5, 2009, GAO denied the protest.
II. DISCUSSION
Before turning, in detail, to plaintiffs claims, we begin with common ground.
A. Standard of Review
The Federal Circuit, in Bannum, Inc. v. United States, 404 F.3d 1346, 1355 (Fed.Cir.2005), instructed that courts must “distinguish ... [a] judgment on the administrative record from a summary judgment requiring the absence of a genuine issue of material fact.” Bannum teaches that two principles commonly associated with summary judgment motions — that the existence of a genuine issue of material fact precludes a grant of summary judgment and that inferences must be weighed in favor of the non-moving party — do not apply in deciding a motion for judgment on the administrative record. Id. at 1356-57. The existence of a question of fact thus neither precludes the granting of a motion for judgment on the administrative record nor requires this court to conduct a full blown evidentiary proceeding. Id.; see also Int’l Outsourcing Servs., LLC v. United States, 69 Fed.Cl. 40, 45-46 (2005).
Bannum’s approach reflects well the limited nature of the review conducted in bid protests. In such cases, this court will enjoin defendant only where an agency’s actions were arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law. 5 U.S.C. § 706(2)(A) (2006); see also 28 U.S.C. § 1491(b)(4) (2006). By its very definition, this standard recognizes the possibility of a zone of acceptable results in a particular ease and requires only that the final decision reached by an agency be the result of a process which “consider[s] the relevant factors” and is “within the bounds of reasoned decisionmaking.” Baltimore Gas & Elec. Co. v. NRDC, 462 U.S. 87, 105, 103 S.Ct. 2246, 76 L.Ed.2d 437 (1983); see Software Testing Solutions, Inc. v. United
The aggrieved bidder must demonstrate that the challengéd agency decision was either irrational or involved a clear violation of applicable statutes and regulations. Banknote Corp., 365 F.3d at 1351, aff'g, 56 Fed.Cl. 377, 380 (2003); see also ARINC Eng’g Servs., LLC v. United States, 77 Fed.Cl. 196, 201 (2007). Moreover, “to prevail in a protest the protester must show not only a significant error in the procurement process, but also that the error prejudiced it.” Data Gen. Corp. v. Johnson, 78 F.3d 1556, 1562 (Fed.Cir.1996). To demonstrate prejudice, “the protestor must show ‘that there was a substantial chance it would have received the contract award but for that error.’” Alfa Laval Separation, Inc. v. United States, 175 F.3d 1365, 1367 (Fed.Cir.1999) (quoting Statistics Inc. v. Christopher, 102 F.3d 1577, 1582 (Fed.Cir.1996)).
B. Alleged Improprieties in the Consideration of BAE’s proposal
Plaintiff asserts that Treasury made three clusters of errors in considering BAE’s proposal, thereby prejudicing EDS’ ability to compete for the subject contract. First, it asseverates that BAE’s proposal contained a materially noneompliant price for CLIN 006 and was ineligible for award. It asserts that, in accepting the BAE’s proposal, Treasury violated 48 C.F.R. § 15.206(a), by failing to amend the RFP to reflect what plaintiff contends were modifications in the requirements associated with the pricing of CLIN 006. Second, EDS contends that Treasury failed to conduct meaningful discussions on an equal basis with all offerors by failing to advise EDS of the aforementioned modifications and that its disaster recovery CLIN prices were too high. Finally, EDS complains that Treasury acted in an arbitrary and capricious fashion in assigning BAE’s technical approach a “Good Rating” despite the latter’s failure to meet the “99.99 percent” SLA requirements regarding data center reliability. The court will discuss these assertions seriatim.
1. Deviation from the Solicitation Terms — CLIN 006 Pricing
“It is hornbook law that agencies must evaluate proposals and make awards based on the criteria stated in the solicitation.” Banknote, 56 Fed.Cl. at 386; see also NEQ, 88 Fed.Cl. at 47; PGBA, LLC v. United States, 60 Fed.Cl. 196, 207, aff'd, 389 F.3d 1219 (Fed.Cir.2004). This requirement is rooted in the Competition in Contracting Act (CICA) and the Federal Acquisition Regulations (FAR), both of which indicate that an agency shall evaluate proposals and assess their qualities solely based on the factors and subfactors specified in the solicitation. See 10 U.S.C. §§ 2305(a)(2)(A)-(3)(A); 48 C.F.R. §§ 15.305(a), 15.303(b); see also NEQ, 88 Fed.Cl. at 47; ManTech Telecomms. & Info. Sys. Corp. v. United States, 49 Fed.Cl. 57, 66 (2001), aff'd, 30 Fed.Appx. 995 (Fed.Cir.2002). If the agency changes any evaluation criterion after issuing the solicitation, it must amend the solicitation and notify the offerors of the changed requirement. See 48 C.F.R. § 15.206(a); see also id. § 15.206(d); SP Sys., Inc. v. United States, 86 Fed.Cl. 1, 18 (2009); Candle Corp. v. United States, 40 Fed.Cl. 658, 663 (1998). Consistent with these precepts, in a case such as this, a protestor must show that: (i) the procuring agency used a significantly different basis in evaluating the proposal than was disclosed; and (ii) the protestor was prejudiced as a result — that it had a substantial chance to receive the contract award but for that error. Banknote, 56 Fed.Cl. at 386-87.
It goes without saying that an agency has “great discretion in determining the scope of an evaluation factoi\”
Further evidence of this lies in the difficulties Treasury encountered in conducting its price reasonableness analysis. The RFP provided that the offerors’ price proposals would be “evaluated for accuracy, completeness, and reasonableness,” and that a price reasonableness analysis would be conducted using the techniques listed in 48 C.F.R. § 15.404-1.
Here, BAE’s price on CLIN 006 was so out of kilter with that of its competitors that Treasury, by its own admission, could not adjust BAE’s price to make it comparable to those of the other offerors in the competitive range. As a result, the agency could not analyze the reasonableness of BAE’s price using methods that rely upon such comparisons, as it had done in analyzing the prices of EDS and [the third offeror]. Rather, in determining that BAE’s price was reasonable, the agency had to compare the competitors’ individual prices for CLINs other than 006 and then to review separately whether BAE’s CLIN 006 price was reasonable by reference to its “user base expansion” pricing. In the court’s view, it is inconceivable that this disjointed evaluation approach was envisioned from the start — that the agency intended to permit, simultaneously, the use of pricing methodologies that were so funda
2. Failure to Conduct Meaningful Discussions
In its second challenge to the award decision, plaintiff asserts that Treasury was compelled to inform the other offerors that it had changed its requirements regarding the pricing of CLIN 006. It argues that the agency’s failure to do so was misleading. EDS also contends that Treasury acted arbitrarily in failing to inform it, during discussions, that its disaster recovery CLIN price was too high.
As the parties agree, agencies generally are required to conduct “meaningful” discussions with all responsible offerors that submit proposals within the competitive range. See 48 C.F.R. § 15.306(d); see also EP Prods., 63 Fed.Cl. at 226; Dynacs Eng’g Co. v. United States, 48 Fed.Cl. 124, 131 (2000) (stating that “[t]he law is well-settled that discussions between a contracting officer and offerors must be meaningful”). However, the FAR emphasizes that “the contracting officer is not required to discuss every area where the proposal could be improved” and that instead “[t]he scope and extent of discussions are a matter of contracting officer judgment.” 48 C.F.R. § 15.306(d)(3). Under these provisions, as this court once observed, “‘[t]he government need not discuss every aspect of the proposal that receives less than the maximum score or identify relative weaknesses in a proposal that is technically acceptable but presents a less desirable approach than others.’ ” Cube Corp. v. United States, 46 Fed.Cl. 368, 384 (2000) (quoting ACRA, Inc. v. United States, 44 Fed.Cl. 288, 295-96 (1999)); see also EP Prods., 63 Fed.Cl. at 226-27; JWK Int’l Corp. v. United States, 49 Fed.Cl. 371, 394 (2001), aff'd, 279 F.3d 985 (Fed.Cir.2002) (“The procuring agency does not have to identify every item that might improve an offeror’s proposal.”); Dynacs, 48 Fed.Cl. at 131. Likewise, an agency need not discuss an offeror’s price unless the price submitted “ “would preclude award to the firm.’ ” DMS All-Star, 90 Fed.Cl. at 669 (quoting Gen. Dynamics-Ordnance & Tactical Sys., 2009 C.P.D. ¶ 217 (2009)). Nevertheless, when conducting discussions with offerors in the competitive range, the agency may not “engage in conduct that ... [flavors one offeror over another.” 48 C.F.R. § 15.306(e); see also Kerr Contractors, 89 Fed.Cl. at 329 (“This regulation does not permit a procuring agency to engage in unequal discus-sions_”).
Plaintiff asserts that because defendant failed to amend the solicitation to reflect new pricing requirements for CLIN 006, it necessarily misled EDS when it did not alert the company to that issue. But, there is no basis for such a per se rule — one in which every failure to amend in violation of FAR § 15.206 would inevitably lead to a corresponding failure to conduct meaningful discussions in violation of FAR § 15.306.
Further discussions were not required here. The application of the modified pricing requirement did not render any portion of EDS’ proposal unacceptable or cause some feature thereof to be classified as a significant weakness. Nor did the agency’s actions result in unequal treatment. Perhaps, the latter would have been the case had Treasury told BAE that its pricing approach was appropriate, but not told EDS that it could likewise remove items from its price. But, that did not happen. Rather, Treasury informed all the final competitors that their Sample Task pricing proposals were incomplete and told both EDS and BAE that they should add items into their pricing — multiple items, in the case of BAE, and six printers, in the case of EDS. The difference is that EDS chose to follow that advice, while BAE did not, apparently based on the view (later vindicated, but ultimately rejected by this court) that its approach was consistent with the RFP’s requirements. Nor was plaintiff misled — at least not prejudicially so. Treasury’s decision to accept BAE’s approach, and error in failing to amend the solicitation to reflect this, both post-dated discussions— in other words, there was nothing wrong with the discussions when they occurred. And had Treasury amended the RFP to include a revised pricing requirement and done nothing else, it would not have been required to conduct a new round of discussions.
Undeterred, plaintiff further complains that Treasury violated the FAR by not telling EDS that its disaster recovery CLIN price was “too high,” while discussing with [the third offeror] that its overall total price and labor costs were “unreasonably high.” But, this contention is at odds with itself for while it hinges on the notion that these two offerors were not treated alike, it fails to come to grips with the essential fact that the concerns raised by the agency with respect to these offerors were not remotely alike. In the case of [the third offeror], the concern regarded its overall price, owing, in particular, to the major price component of labor costs. Moreover, that price was viewed as so high as to render the proposal potentially unacceptable. EDS’ pricing issues, by comparison, neither involved its overall price nor, correspondingly, threatened the acceptability of its offer. Rather, the agency’s much more limited concerns focused only on EDS’ price as to a single CLIN and involved only competitiveness. That Treasury discussed price with [the third offeror], but not with plaintiff, thus did not give rise to the sort of unequal treatment that would violate the FAR.
Because both cost and non-cost factors must be considered and the agency has full discretion to rank the importance of the factors, a downward cost adjustment may not always affect the award. Therefore, cost is not always material, and does not automatically mandate discussions.
JWK Int'l, 279 F.3d at 988.
3. Evaluation of Technical Proposal— Data Center
EDS further argues that BAE’s proposal did not comply with the SLAs that established 99.99-pereent availability for certain data center services, including e-mail, file/print and application transport. It treats as virtually self-evident that the “Tier II” data center offered by BAE could not meet the higher system-availability requirements of the RFP. It was arbitrary and capricious, EDS further contends, for Treasury to accept BAE’s proposal in this regard and complains that the agency should have assigned an unacceptable rating (or at least not a good rating) to BAE’s managed services solution factor. But, these claims hinge on several major assumptions that turn out to be false.
First, plaintiff wrongly assumes that the SLAs established solicitation requirements that, like the others in the RFP, had to be fully met by the offerors in their proposals. But, it appears that the SLAs were different. A review of the entire RFP suggests that their primary, if not exclusive, function was to establish contractual benchmarks for measuring the awardee’s future performance. In this regard, the RFP indicated that the contract would offer the awardee incentives for meeting these benchmarks and discen-tives if it did not — an approach that seems to treat compliance with these SLAs more as a matter of contract administration than as something to be evaluated in the absolute terms that EDS suggests.
One might ask — as plaintiff does — how a data center that is available 99.75 percent of the time can meet a requirement for 99.99-pereent availability? But, this question assumes that the latter requirement existed— and it did not. The RFP did not require the data center to be rated a “Tier IV” facility— the type that would provide for 99.99-percent availability under the Uptime Institute’s classifications. Indeed, it made no reference whatsoever to the Uptime Institute’s classification system, nor, for that matter, to any independent requirements for the availability of the data center itself. There is, moreover, no indication that the Uptime Institute’s classification system correlates in any meaningful, let alone determinative, way with the SLAs’ reliability benchmarks, and, in particular, no indication that the 99.99-pereent-availability-benchmark in the SLAs is calculated in the same fashion as the 99.75-per-cent availability-figures used in the Institute’s classifications. It appears, rather, that the two numbers bear little relation to each other for the Institute’s classifications rely on both scheduled and unscheduled downtime, while the RFP’s 99.99-percent-availability benchmarks consider only the latter. And there are indications in the record that the classification system and RFP do not use the same periods for measuring compliance — obviously, no minor point when one is measuring availability to the hundredths of a percent. Given these differences, it is more than conceivable that, in combination with other hardware, a “Tier II” facility could meet the SLA benchmarks for services such as e-mail. Certainly, plaintiff has provided no hard facts to the contrary, let alone enough to permit this court to conclude that Treasury’s finding was arbitrary and capricious.
C. Prejudice
“Not every error by a [contracting officer] justifies overturning an award.” United Int’l Investigative Servs., Inc. v. United States, 42 Fed.Cl. 73, 87 (1998), aff'd, 194 F.3d 1335, 1999 WL 302422 (Fed.Cir.1999). Rather, when a challenge is brought on the ground that a procurement involved a violation of a regulation or procedure, “ ‘the disappointed bidder must show a clear and prejudicial violation of applicable statutes or regulations.’” Banknote Corp., 365 F.3d at 1351 (quoting Impresa Construzioni Geom. Domenico Gamfi v. United States, 238 F.3d 1324, 1333 (Fed.Cir.2001)); see also Axiom Res., 564 F.3d at 1381; Centech Group, Inc. v. United States, 554 F.3d 1029, 1037 (Fed.Cir.2009). As noted above, to demonstrate prejudice, a “protestor must show ‘that there was a substantial chance it would have received the contract award but for that error.’” Alfa Laval Separation, 175 F.3d at 1367 (quoting Statistica, 102 F.3d at 1582); see also Bannum, 404 F.3d at 1358; Galen Med. Assocs., 369 F.3d at 1331; Int’l Outsourcing Servs., 69 Fed.Cl. at 47. “This test is more lenient than showing actual causation,” the Federal Circuit has instructed, for the protestor need not “show[ ] that but for the errors [it] would have won the contract.” Bannum, 404 F.3d at 1358; see also Alfa Laval, 175 F.3d at 1367; Data Gen. Corp. v. Johnson, 78 F.3d 1556, 1562 (Fed.Cir.1996).
Several cases hold that, to demonstrate prejudice in the context of a failed amendment, the protestor must show that it “would have altered its proposal to its competitive advantage had it been given the opportunity to respond to an altered requirement.” Warren Electrical Constr. Corp., 90-2 C.P.D. ¶ 34 (1990); see also Saratoga
Now, of course, some of the difference in the total prices here was driven by the offer-ors’ different approaches to pricing the Sample Task. And, it, therefore, is left open for plaintiff to argue that a portion of the existing price differential could be attributed to defendant’s failure to amend the solicitation to reflect its view as to the correct pricing of the Sample Task. Plaintiff’s CLIN 006 price and thus its overall price doubtlessly would have been lower had it known that a pricing approach like BAE’s was permissible, if not preferable. But, how much lower — and to what effect? In the court's view, any such differences would have been inconsequential. In fact, Treasury more than accounted for its error in failing to amend the RFP, by adjusting, in its best value analysis, EDS’ overall price to exclude all hardware and software costs from the latter’s pricing proposal. Indeed, while the SSA subtracted $[ ] of these costs from EDS’ price, it did not reduce, at all, BAE’s price for the $[ ] of software and hardware costs that the latter actually included in its worksheet. By virtue of this one-sided adjustment, the spread between the two competitors’ prices shrank considerably, from $49,125,129 to $[ ]. Yet, even when reweighing this much smaller differential, the SSA unhesitatingly concluded that BAE’s proposal represented the best value to Treasury. Accordingly, this is not a situation where the court must speculate as to what a new award decision would be on remand or how such a decision would be rationalized by the agency. Rather, the source selection documents make clear that even under the best of scenarios — one better than EDS could have dreamed to generate in revised proposals — plaintiff would not have received the contract.
It is no answer to contend, as plaintiff does, that prejudice ought be presumed where there is a violation of a procurement regulation framed in mandatory terms. EDS claims that FAR § 15.206(a) is such a regulation for it declares that if the government changes its requirements, the contracting officer “shall” amend the solicitation. Plaintiff argues that this regulation would be rendered little more than a toothless exhortation, if an agency, rather than amending a solicitation, could blot out any prejudice associated with the violation. At first blush, this argument seems merely to enforce the plain meaning of the provision at issue. But, of course, the fundamental question posed by the prejudice inquiry is whether a provision should be enforced — the whole purpose of that requirement is to prevent courts from interfering with procurements based on mere technical violations of the rules. If prejudice is to be “deemed” found in a case such as this, what is to prevent it from being presumed away in every case involving a so-called “mandatory” FAR provision? The answer, in a word, is — nothing. To take such a course, the court would have to untether its bid protest jurisdiction from its legal moorings — a result incompatible not only with the Federal Circuit’s repeated instruction that a protest may be sustained only upon a “prejudicial” violation of a statute or regulation, see, e.g., Axiom, 564 F.3d at 1381 (citing Impresa, 238 F.3d at 1333), but with the Administrative Dispute Resolution Act of 1996, Pub.L. No. 104-320, § 12, 110 Stat. 3870, from which our jurisdiction derives. It is the latter statute, after all, that requires this court to employ the arbitrary and capricious standard of 5 U.S.C. § 706 — a standard that comes interwoven with the admonition that “due account shall be taken of the rule of prejudicial error.” Id. at § 706.
Properly construed, Alfa Laval thus avails plaintiff naught. For one thing, no technical requirement was violated here, let alone a mandatory one. Rather, the issue was one of pricing. Various provisions in the FAR suggest that, when dealing with a negotiated, “best value” procurement such as this one, there is flexibility in dealing with deviations from an RFP’s pricing terms, provided that the agency ultimately can determine that the overall price is reasonable; that any unbalanced pricing, if it exists, does not pose an unacceptable level of risk; and, of course, that a proposal represents the best value. See 48 C.F.R. § 15.404-l(b), 1(g)(2); see also Diversified Capital, Inc., 2004 C.P.D. ¶ 242 (2004).
In the final analysis, the court remains unpersuaded that plaintiff was prejudiced by the error committed by Treasury in failing to amend the solicitation. Every indication instead is that the impact of that error was dwarfed by the huge price differential between the relevant proposals and more than offset by the adjustments made by the SSA in his best value determination. To conclude otherwise would be to depart not only from well-accepted concepts of what constitutes prejudice, but from commercial reality. Absent a showing of prejudice, plaintiffs case must fail, even though it has been marginally successful in demonstrating that an error occurred in the subject procurement.
III. CONCLUSION
This court need go no further. Measured by the appropriate standard of review, Treasury’s conduct, to the extent erroneous, was not prejudicial to plaintiff. The injunctive relief requested by plaintiff, therefore, is inappropriate.
In consideration of the above—
1. Plaintiffs motion for judgment on the administrative record is DENIED and defendant’s and defendant-intervenor’s cross-motions for judgment on the administrative record are GRANTED.
2. This opinion shall be publicly released, as issued, after May 11, 2010, unless the pai’ties identify protected and/or privileged materials subject to redaction prior to said date. Said materials shall be identified with specificity, both in terms of the language to be redacted and the reasons for that redaction.
IT IS SO ORDERED.
. The RFP defined "network infrastructure” as "the collection of network router, switch, hub, and concentrator devices; MS Active Directory, Domain Controller, DNS [domain name system] and DHCP [dynamic host configuration protocol] servers, remote access/VPN [virtual private network] concentrators; the firewall, IDS/IPS [intrusion detection system/intrusion prevention system], encryption and other network security devices; and the SNMP [simple network management protocol]-based network and system management devices.”
. This worksheet looked as follows:
[[Image here]]
. The Managed Service Solution factor contained four sub-factors, listed in descending order of importance: Technical Approach, Management Plan, Key Personnel, and Sample Task Response. The Performance Risk factor contained two sub-factors, in descending order of importance: Past Performance and Corporate Experience and Capabilities. The Price and Small Business Participation factors did not have sub-factors.
. For example, an offeror could receive a good rating for its technical approach if the proposal "fully me[t] or somewhat exceed[ed] all solicitation requirements, and offer[ed] one or more strengths not offset by weaknesses.”
. The Source Selection Plan contained specific instructions for evaluating the price of the Sample Task scenario. In this regard, it stated that various teams would "evaluate [the] Offeror’s use of proposed labor categories, rates and unit prices of hardware/software."
. The Uptime Institute provides a set of Tier Performance Standards that use a series of benchmarks to compare the uninterruptible availability of customized data centers to each other. Currently, there are four tiers of availability, ranging from Tier I at 99.67-percent availability to Tier IV at more than 99.99-percent availability.
. As BAE had done initially, its final Sample Task pricing worksheet reflected certain items of hardware and software, as follows:
Catalogue Item Description Hours/Quantity Unit Price Total
500GB SAN Space — Hardware Purchase 1 $[] $[]
500 GB SAN Space — Hardware Maintenance 1 $ $ (incl in Purchase)
Oracle License 100 $[] $[]
Oracle License — Maintenance 100 $[] $[]
Firewall — Hardware Purchase 2 $[] $[]
Firewall — Management Software (incl in 2 $ $ Purchase)
Firewall — Hardware Maintenance (incl in 2 $ $ Purchase)
Accordingly, as it had done it its initial proposal,
BAE’s CLIN 006 pricing chart listed some items
. Bannum was based upon RCFC 56.1, which, in 2006, was abrogated and replaced by RCFC 52.1. The latter rule was designed to incorporate the decision in Bannum. See RCFC 52.1, Rules Committee Note (2006); see also NVT Techs., Inc. v. United States, 73 Fed.Cl. 459, 462 n. 3 (2006); Bice v. United States, 72 Fed.Cl. 432, 441 (2006), aff'd, 2007 WL 2032849 (Fed.Cir. July 12, 2007).
. In Bannum, the Federal Circuit noted that, in Banknote Corp. of Am. Inc. v. United States, 365 F.3d 1345, 1352-53 (Fed.Cir.2004), it had erroneously conflated the standards under RCFC 56 and 56.1, albeit in dicta. In this regard, Bannum stated that—
Although it never reached the factual question of prejudice, the Banknote II court added that it is the trial and appellate courts' task to "determine whether there are any genuine issues of material fact as to whether the agency decision lacked a rational basis or involved a prejudicial violation of applicable statutes or regulations.” This language equates a RCFC 56.1 judgment to a summary judgment under RCFC 56 and is unnecessary to the Banknote II holding. Because the court decided the issue by an interpretation of the solicitation, e.g., making a legal determination, the court in Banknote II did not need Lo consider whether the trial court overlooked a genuine dispute or improperly considered the facts of that case.
404 F.3d at 1354. Prior decisions of this court had similarly erred. See, e.g., JWK Int’l Corp. v. United States, 49 Fed.Cl. 371, 387 (2001), aff’d, 279 F.3d 985 (Fed.Cir.2002).
. In Axiom, the Federal Circuit noted that the "supplementation of the record should be limited to cases in which 'the omission of extra-record evidence precludes effective judicial review.’" 564 F.3d at 1380 (quoting Murakami v. United States, 46 Fed.Cl. 731, 735 (2000), aff'd, 398 F.3d 1342 (Fed.Cir.2005)). In forceful terms, the Federal Circuit rejected the lenient approach to the use of extra-record evidence reflected in Esch v. Yeutter, 876 F.2d 976, 991 (D.C.Cir.1989), noting that the latter decision: (i) "departs from fundamental principles of administrative law as articulated by the Supreme Court;” (ii) has “questionable” vitality "even within the D.C. Circuit ... in light of more recent opinions by that court which demonstrate a more restrictive approach to extra-record evidence;" and (iii) at all events, "is not the law of this circuit.” Axiom, 564 F.3d at 1380-81. As this court has subsequently noted, “[wjhile Axiom undoubtedly permits limited supplementation of the record with evidence that does not involve the agency's procurement decision (e.g., evidence as to whether a plaintiff would experience irreparable harm), it makes clear that any courl in this circuit that relies upon Esch to supplement the administrative record more broadly does so at peril of reversal.” NEQ, 88 Fed.Cl. at 47 n. 6.
. As noted by the Federal Circuit, "[pjrocurement officials have substantial discretion to determine which proposal represents the best value for the government.” E.W. Bliss Co. v. United States, 77 F.3d 445, 449 (Fed.Cir.1996); see also Galen Med. Assocs., Inc. v. United States, 369 F.3d 1324, 1330 (Fed.Cir.2004); TRW, Inc. v. Unisys Corp., 98 F.3d 1325, 1327-28 (Fed.Cir.1996); LaBarge Prods., Inc. v. West, 46 F.3d 1547, 1555 (Fed.Cir.1995) (citing Butroughs Corp. v. United States, 223 Ct.Cl. 53, 617 F.2d 590, 597-98 (1980)); EP Prods., Inc. v. United States, 63 Fed.Cl. 220, 223 (2005), aff'd, 163 Fed.Appx. 892 (Fed.Cir.2006).
.A review of Federal Circuit cases indicates that this prejudice analysis actually comes in two varieties. The first is that described above— namely, the ultimate requirement that a protestor must show prejudice in order to merit relief. A second prejudice analysis is more in the nature of a standing inquiry. In this regard, the Federal Circuit has held that “because the question of prejudice goes directly to the question of standing, the prejudice issue must be reached before addressing the merits.” Info. Tech. & Applications Corp. v. United States, 316 F.3d 1312, 1319 (Fed.Cir.2003); see also Myers Investigative & Sec. Servs., Inc. v. United States, 275 F.3d 1366, 1370 (Fed.Cir.2002); Overstreet Elec. Co., Inc. v. United States, 59 Fed.Cl. 99, 109 n. 5 (2003). Cases construing this second variation on the prejudice inquiry have held that it requires merely a "viable allegation of agency wrong doing,” with " 'viability' here turning on the reasonableness of the likelihood of prevailing on the prospective bid taking the protestor's allegations as true.” McKing Consulting Corp. v. United States, 78 Fed.Cl. 715, 721 (2007); see also 210 Earll, LLC v. United States, 77 Fed.Cl. 710, 718-19 (2006); Textron, Inc. v. United States, 74 Fed.Cl. 277, 284-85 (2006). (This "viability" standard is
. See also NEQ, 88 Fed.Cl. at 48 n. 8 (citing cases); Bean Stuyvesant, LLC v. United States, 48 Fed.Cl. 303, 321 (2000); Dubinsky v. United States, 43 Fed.Cl. 243, 266 (1999).
. Forestry Surveys and Data v. United States, 44 Fed.Cl. 493, 499 (1999) (citing John Cibinic Jr. & Ralph C. Nash, Jr., Formation of Government Contracts 830 (3rd ed.1998) (hereinafter "Cibinic & Nash”)); see also Kerr Contractors, Inc. v. United States, 89 Fed.Cl. 312, 327 (2009); NEQ, 88 Fed.Cl. at 48.
. The evaluation of price reasonableness is designed to prevent the government from paying too high a price for a particular contract. See DMS All-Star Joint Venture v. United States, 90 Fed.Cl. 653, 663 n. 11 (2010); Serco, Inc. v. United States, 81 Fed.Cl. 463, 494 n. 48 (2008); see also Ralph C. Nash & John Cibinic, “Cost and Price Analysis; Understanding the Terms," 9 No. 1 Nash & Cibinic Rep. ¶5 (1995) (“The purpose of a price reasonableness determination is to ascertain that the Government is not paying too high a price.”).
. Plaintiff, of course, is quite correct that had Treasury amended the solicitation, it would have been required to notify the offerors. See 48 C.F.R. 15.206(c). But, neither FAR § 15.206 nor FAR § 15.306 treat such a notice as the equivalent of discussions. Compare 48 C.F.R. § 15.306(a)-(b) with id. at § 15.306(d) (distinguishing between other types of communications and discussions (or negotiations)).
. In this regard, recall that the RFP stated that "[t]he Government reserves the right to award a contract on the basis of initial offers received, without conducting discussions, in accordance with Federal Acquisition Regulations (FAR) 52.215-1 (f), Contract Award. Therefore, initial offers should contain the offeror’s best terms from both a technical and a pricing perspective.” See also 48 C.F.R. § 15.306(a)(3) (discussing when awards may be made without discussions); Galen Med. Assocs., 369 F.3d at 1332-33.
. Plaintiff argues that, to the extent it finds ambiguity in the CLIN 006 pricing or the SLAs that establish the 99.99-percent-availability benchmarks, the court should determine that Treasury failed to conduct meaningful discussions when it neglected to clarify such ambiguities. An agency’s failure to clarify known ambiguities in an RFP may constitute a breach of the discussion duty. See Bank of America, 2001 C.P.D. ¶ 137 (2001) (finding a lack of meaningful discussion when the agency failed to clarify a recognized ambiguity in the solicitation that led to significant disparity between offers). However, in this case the court has found no ambiguity in the cited portions of the RFP and thus need not address plaintiff's argument further.
. See also DMS All-Star, 90 Fed.Cl. al 669 (“unless an offeror's costs constitute a significant weakness or deficiency in its proposal, the contracting officer is not required to address in discussions costs that appear to be higher lhan those proposed by other offerors”); AshBritt, Inc. v. United States, 87 Fed.Cl. 344, 372 (2009); Banknote Corp., 56 Fed.Cl. at 385.
. Plaintiff claims that the SLAs requiring 99.99-percenl availability were mandatory minimum requirements, such that BAE's alleged failure to meet the requirement rendered it ineligible for award. Mandatory mínimums are "essentially pass/fail in nature and may lead to the outright rejection of a proposal that falls short.” Man-Tech., 49 Fed.Cl. at 67. They “must be clearly identified as such within the solicitation” using language to pul offerors on notice that "failure to comply with the requirement will lead to outright rejection of the proposal.” Id. In this case, the SLAs cannot fairly be interpreted as mandatory minimum requirements because they were not pass/fail in nature. The RFP clearly indicated that the agency would evaluate an offeror’s "probability of success” in meeting the SLAs, and established a system of incentives and disincentives to encourage compliance with the SLAs during performance. These factors militate strongly against a finding that the SLAs constituted mandatory minimum requirements, and the court will not make such a determination.
. See Banknote Corp., 56 Fed.Cl. at 384 ("[A]n offeror's mere disagreement with the agency's judgment concerning the adequacy of the proposal is not sufficient to establish that the agency acted unreasonably.” (quotation and citation omitted)); JWK Int’l Corp., 52 Fed.Cl. at 660 ("[N]aked claims, by all appearances unsupported by anything in the record, fall far short of meeting the heavy burden of demonstrating that ... findings were the product of an irrational process and hence arbitrary and capricious.”).
. As noted, the SSA reduced EDS' hardware and software price to zero while leaving BAE’s hardware and software costs intact. Had EDS altered its CLIN 006 pricing proposal (and, correspondingly, its UBE pricing) to conform to BAE’s approach, it would have had to include some hardware and software components not included in its UBE, thus bringing its CLIN 006 hardware and software costs above zero. Alternatively, had Treasury required BAE to modify its CLIN 006 proposal to include all hardware and software components, BAE's pricing would have increased according to the cost of the newly included items. Those costs, however, undoubtedly would have tracked BAE's on-line catalog pricing proposed in CLIN 005. This is significant for while BAE proposed catalog prices that were at a[ ]-percent discount off the lowest price available, EDS proposed [] discount, strongly suggesting that, if EDS and BAE employed the same approach, BAE still would have had lower CLIN 006 hardware and software prices than EDS. Every indication, then, is that EDS made out much better under the approach taken by the SSA than it would have under a new proposal.
To be sure, EDS submitted a declaration from one of its corporate officials claiming that, had it known Treasury did not expect offerors to include Sample Task hardware and software costs
.See Data Gen., 78 F.3d at 1563 (prejudice not found when, despite pricing error, protestor's price remained substantially higher); Candle Corp., 40 Fed.Cl. at 665 ("If the protestor's price would have remained significantly higher than the awardee's had there been no illegality, and there is no evidence that the SSA's award decision would have changed, it is unlikely the court will find prejudice.”); see also Moore’s Cafeteria Servs. v. United States, 77 Fed.Cl. 180, 188 (2007), aff’d, 314 Fed.Appx. 277 (Fed.Cir.2008) (no prejudice where contracting officer noted that she would still have awarded the contract to the same offeror even if the independent govemment estimate used to evaluated prices was flawed).
. The Supreme Court has held that such prejudice requirements are designed to prevent reviewing courts from becoming "impregnable citadels of technicality." Kotteakos v. United States, 328 U.S. 750, 759, 66 S.Ct. 1239, 90 L.Ed. 1557 (1946); see also Shinseki v. Sanders, - U.S. -, 129 S.Ct. 1696, 1705, 173 L.Ed.2d 532 (2009) (construing a comparable prejudice requirement applied in the Veterans Court via 38 U.S.C. § 7261(b)(2)). Notably, in dealing with such prejudice requirements in various administrative law contexts, the Supreme Court has "warned against courts' determining whether an error is harmless through the use of mandatory presumptions and rigid rules rather than case-specific application of judgment, based upon examination of the record.” Id. at 1704-05.
. See FAR § 2.101 (stating that "shall denotes the imperative”); see also, e.g., FAR § 15.404-2 (indicating that the contracting officer “shall” request a variety of information to support proposal analysis); FAR§ 15.606 — 1 (c) ("If a proposal is rejected because the proposal does not meet the requirements of paragraph (a) of this subsection, the agency contact point shall promptly inform the offeror of the reasons for rejection in writing and of the proposed disposition of the
. Obviously, different considerations might exist if we were dealing with an invitation for bids that anticipated sealed-bidding. In the latter instance, for example, even relatively minor variations from the pricing terms may lead to a deler-mination that a bid is nonresponsive. See 48 C.F.R. § 14.301; 14.404 — 2(d)(2)-(3). But, that is not the situation here — indeed, the pricing terms at issue related only to a single sample task.
. See, e.g., ManTech, 49 Fed.Cl. at 70-71; Pacific Consol. Indus., 87-2 C.P.D. ¶ 548 (1987); Keco Indus., Inc., 84-2 C.P.D. ¶491 (1984); see also Data Gen., 78 F.3d at 1565 ("We know of no principle or precedent ... that requires or even suggests disqualifying an otherwise qualified bidder because of inconsistencies in its quoted prices.”); Info. Sciences Corp. v. United States, 80 Fed.Cl. 759, 781 (2008).
. See also Myers Investigative and Sec. Servs., Inc. v. United States, 47 Fed.Cl. 605, 620 (2000), aff'd, 275 F.3d 1366 (Fed.Cir.2002).
. Two leading commentators, in fact, suggest that an amendment may not be required under FAR § 15.206(a), unless there is a “significant impact on competition.” Cibinic & Nash, supra, at 770. As described by Professors Cibinic and Nash, "[a] significant impact on competition occurs when (1) mandatory specifications or terms and conditions are changed, and (2) offerors not receiving notice of the changes would be prejudiced.” Id. at 770; see also id. at 773 ("Failure to amend an RFP has ... been excused where the protester was unable to demonstrate that it was prejudiced by the lack of notice.”). It makes little practical difference here whether the better formulation is that no obligation to amend the RFP arose because there was no prejudice to EDS, or that there was an obligation to amend, but that no relief may be afforded owing to the same lack of prejudice — for in either instance, plaintiff loses.