DocketNumber: No. 98-12359-SSM; Civ.A. No. 99-1328-A
Judges: Ellis
Filed Date: 11/24/1999
Status: Precedential
Modified Date: 11/2/2024
MEMORANDUM OPINION
This bankruptcy appeal presents an unsettled question of Virginia law, namely, whether the doctrine of merger by deed extinguishes a purchaser’s right to sue on a contractual clause requiring settlement by a certain date, when the purchaser accepts tardy delivery of the deed without specifically reserving the right to seek damages for delay.
I
This bankruptcy appeal is an outgrowth of appellee Diane Tribby’s divorce from her husband, Troy Tribby. As a consequence of the couple’s divorce proceedings, certain real property jointly owned
Meanwhile, in July 1998, appellants filed a proof of claim against appellee’s estate, seeking both specific performance of the contract for the sale of the real estate, as well as damages arising from delay in consummating the transaction. Appellee, while appealing the Bankruptcy Court’s grant of relief, filed a plan that declared the contract an avoidable executory contract. The district court denied appellee’s appeal of the grant of relief, and also denied a further stay pending appeal to the Fourth Circuit Court of Appeals. The parties then proceeded to closing, which occurred on December 2, 1998, when ap-pellee and her husband tendered a deed conveying the property to appellants.
Appellants, having received the deed to the property, now seek damages arising from appellee’s eight month delay in deliv
On these facts, the Bankruptcy Judge found that appellee breached the term of the contract requiring settlement by March 28, 1998, and that if such a breach established liability to appellants, appellee would be liable for the tax bill, as well as additional expenses of $850. The Bankruptcy Judge ruled, however, that the doctrine of merger by deed extinguished ap-pellee’s liability under the contract’s time of performance clause. In a thoughtful opinion delivered from the bench, the Bankruptcy Judge concluded that the date fixed for the sale of property “went to the very heart of the transaction,” was not collateral to the passage of title, and was therefore extinguished by appellants’ acceptance of the deed. In his view, because the deed was silent as to the earlier deadline, appellants could not seek damages for delay. On a motion to reconsider, the Bankruptcy Judge rejected appellants’ argument based on the contract’s survival clause, and reaffirmed that the time of performance clause was fundamentally inconsistent with delivery of the deed at a later date.
On appeal, appellants claim the Bankruptcy Judge misconstrued and misapplied Virginia’s doctrine of merger, and improperly ignored the contract’s survival clause. The question presented is thus whether Virginia’s doctrine of merger dictates that a deed conveying property extinguishes a right to seek damages for delay pursuant to a term in the sale contract. Because the Bankruptcy Court’s holding involves the application of the law, appellate review is de novo. In re Stanley, 66 F.3d 664, 667 (4th Cir.1995).
II
The doctrine of merger in the sale of real property is a rule of contract construction by which certain aspects of the initial executory contract are subsequently extinguished by the deed, an “instrument of higher dignity.”
The answer to the second question is found in Virginia decisional law on the merger doctrine. In concluding whether a clause is merged into the deed, the Supreme Court of Virginia identified the following factors as relevant: (i) whether the term was “collateral to the sale of the property,” (ii) whether it “qualified], or in any way affectfed], title to the land,” (in) whether it was one “with which a title examiner would necessarily be concerned,”
Although the Supreme Court of Virginia has not squarely considered whether time of performance clauses are collateral to the passage of title, it has ruled that a variety of analogous provisions are collateral in this respect, including rental income guarantees made by the seller,
Courts in other states have similarly concluded that a term fixing the time for settlement is not merged into the deed once the deed is accepted.
The soundness of a rule is often confirmed by an examination of the effects of the contrary rule. That is the case here; were a contractual time of performance obligation to be merged into the deed, a tardy vendor could avoid the liability contemplated by the time of performance clause simply by tendering a deed that lacked an express reservation of delay damages. The vendee would then face a dilemma: either accept the deed and forfeit the cause of action, or reject the deed and sue the vendor for specific performance and damages. But a vendee already aggrieved by a tardy vendor should not be forced to reject the deed and proceed to litigation on the entire transaction to preserve his right to seek damages for an element collateral to both the fact of conveyance and the substance of what was conveyed. Indeed, as the Christensen court noted, it is illogical to allow a vendee to sue a tardy vendor for specific performance and damages where the vendor has not yet tendered the deed, while foreclosing the damages remedy merely because tardy performance is tendered. See 343 P.2d at 344.
Moreover, the purposes of the merger doctrine are not met by the contrary rule. On the one hand, the merger doctrine protects the integrity of the deed by ensuring that documents external to the deed involved in the sales transaction cannot alter the meaning, scope, or quality of the deed, or affect the fact of conveyance itself.
Appellee contends that appellants affirmatively waived the time of performance clause in the course of negotiations with appellee. The current record is inconclusive on this question, and, in any event, appellants contend it is raised for the first time on appeal. If this waiver argument was not made in the proceedings before the Bankruptcy Court, it cannot be made for the first time here, unless a failure to allow the argument to be raised constitutes “plain error” or “a fundamental miscarriage of justice,” and no such error or miscarriage of justice is apparent. See Muth v. United States, 1 F.3d 246, 250 (4th Cir.1993). Thus, on remand, the Bankruptcy Court should determine (i) whether appellee properly raised the waiver argument before the Bankruptcy Court, and (ii) if so, whether appellants voluntarily waived the time of performance clause in some way other than by acceptance of the deed.
Accordingly, the Bankruptcy Court’s orders of June 22, 1999, allowing appellants’ claim in a reduced amount, and July 14, 1999, denying appellants’ motion for reconsideration, must be vacated, and this case remanded for further proceedings consistent with this memorandum opinion.
The Clerk is directed to forward copies of this Memorandum Opinion to all counsel of record. An appropriate order will enter.
. Appellee lived and operated her business on this property.
. The survival clause stated as follows: "The provisions [of this contract] shall survive delivery of the deed and shall not be merged therein.” Regional Sales Contract ¶ 33.
. See 26 U.S.C. § 1031 (authorizing so-called "like kind,” tax free exchanges).
. Empire Management & Development Co., Inc. v. Greenville Associates, 255 Va. 49, 52, 496 S.E.2d 440, 442 (1998); Miller v. Reynolds, 216 Va. 852, 854, 223 S.E.2d 883, 885 (1976). This is based on the "elementary principle” governing all agreements that "a later agreement, in more solemn form, is considered an execution of the preceding negotiations leading up to its execution.” Charles S. Parnell, Deed as Superseding or Merging Provisions of Antecedent Contract Imposing Obligations upon the Vendor, 38 A.L.R. 1310, § 3 (1954).
.See 5C Michie’s Jurisprudence of Virginia and West Virginia, Deeds § 107 (1998) [hereinafter Michie's Jurisprudence, Deeds ] ("Until consummated by deed, an executory contract
. See also Miller v. Reynolds, 216 Va. at 855, 223 S.E.2d at 885; 5C Michie's Jurisprudence, Deeds, supra, § 107 (1998) ("The general rule is that all articles of agreement for the sale of land are merged in and extinguished by a subsequent deed thereof between the parties.”).
. See also Davis v. Tazewell Place Associates, 254 Va. 257, 262, 492 S.E.2d 162, 165 (1997); Miller v. Reynolds, 216 Va. at 855, 223 S.E.2d at 885.
. See Miller v. Reynolds, 216 Va. at 855, 223 S.E.2d at 885 (noting that the "deed is a mere transfer of title” and that the contract "may, and often does, contain many provisions which the execution of the deed neither adds to nor takes away from”) (quoting Collins v. Lyon, 181 Va. 230, 245, 24 S.E.2d 572, 579 (1943); citing Sale v. Figg, 164 Va. 402, 180 S.E. 173 (1935)) (internal quotation marks omitted); 5C Michie's Jurisprudence, Deeds, supra, at § 107 (“[T]he deed effects a merger only to the extent that it is contemplated that the deed should be a performance of the contract.”); see also Parnell, supra note 4, ("[T]he deed is actually intended in most cases as an execution only of the contract to convey.”).
. See Miller v. Reynolds, 216 Va. at 855, 223 S.E.2d at 885 ("[P]arol evidence is admissible to show ... all other parts of the transaction, not inconsistent with the recitals in the deed, provided the fact of conveyance is not affected by it.”) (internal quotation marks and citations omitted) (emphasis added).
Corbin stated this general rule as follows: The deed of conveyance is delivered as a part performance of the contract; it is almost never assented to as a complete "integration” of the contract. The conveyance may or may not be accepted by the purchaser as full satisfaction of some or all of the vendor’s promissory duties; it is almost never assented to by the purchaser as a complete written statement of what those duties are, and even less often is it assented to by the vendor as a complete statement of the duties assumed by the purchaser. Parol evidence is practically always admissible to show that the consideration for the conveyance is not accurately stated in the deed, if the purpose for which it is offered is the enforcement of promises made by either party and not to affect to the validity of the deed as a conveyance.
6 Arthur Linton Corbin, Corbin on Contracts § 1319 (1962).
. See Miller v. Kemp, 157 Va. 178, 201, 160 S.E. 203, 209 (1931) ("The very fact that the final instrument of conveyance, the deed, differs from the original contract and was accepted by both [parties] is evidence of a change in their original agreement.”); Woodson, 128 Va. at 656, 104 S.E. at 795 ("All inconsistencies between the prior contract and the deed must be determined by the latter alone....”).
. See Davis v. Tazewell Place Associates, 254 Va. 257, 262, 492 S.E.2d 162, 165 (1997); Miller, 216 Va. at 855, 223 S.E.2d 883 ("There are many things pertaining to the contract which it is manifest are never inserted in a deed”) (quoting Collins v. Lyon, 181 Va. 230, 24 S.E.2d 572 (1943); other citations omitted); Woodson, 128 Va. at 656, 104 S.E.
. The parties, of course, may have intended the delivery of the deed to erase the contractual obligation created by the time of performance clause, but that is evidence of waiver or of accord and satisfaction, not a conflict between the terms. See 6 Corbin, supra, § 1319 (noting that the conveyance of the deed "may or may not be accepted by the purchaser as full satisfaction of some or all of the vendor’s promissory duties”).
. Davis, 254 Va. at 263, 492 S.E.2d at 165; see also Miller v. Reynolds, 216 Va. at 855-56, 223 S.E.2d at 885.
. Miller v. Reynolds, 216 Va. at 856, 223 S.E.2d 883.
. See Empire Management, 255 Va. at 54, 496 S.E.2d at 443 (considering whether the parties intended the rent guarantees to be extinguished with the deed); see also Continental Life Ins. Co. v. Smith, 41 N.M. 82, 64 P.2d 377 (1936) (noting that "if the stipulation has reference to title, possession, quantity, or emblements of the land, it is generally, but not always, held to inhere in the very subject-matter with which the deed deals, and is merged therein”).
. Cf. Davis, 254 Va. at 263, 492 S.E.2d at 165 (holding that a warranty to construct a townhouse in a good and workmanlike manner was collateral to the sale of property).
. See Empire Management, 255 Va. at 54, 496 S.E.2d at 443.
. See Davis, 254 Va. at 263, 492 S.E.2d at 165.
. See Miller v. Reynolds, 216 Va. at 853-54, 223 S.E.2d at 884-85.
. See Continental Life Ins. Co. v. Smith, 41 N.M. 82, 64 P.2d 377 (1936) ("[A] stipulation to deliver a deed at a certain time ... could not merge in a deed, but it may be intentionally waived or surrendered.”); Christensen v. Slawter, 173 Cal.App.2d 325, 343 P.2d 341 (1959) (“[U]nder [the circumstances of the case] the acceptance of a tardy conveyance should not be held to constitute a waiver of the purchaser's right to sue for the damages resulting from the delay.”); Houston & T.C.R. Co. v. Wright, 15 Tex.Civ.App. 151, 38 S.W. 836 (1897) (holding that acceptance of the deed did not foreclose an action for damages from delay).
Indeed, the Nebraska Supreme Court, in deciding a separate question of merger law, assumed without discussion that a clause fixing the time of performance does not merge with the deed. See Purbaugh v. Jurgensmeier, 684, 240 Neb. 679, 483 N.W.2d 757, 762 (1992) ("[T]erms such as ... date of closing ... are normally not repeated in the deed and therefore are not merged with the deed instrument.”).
Only one court, on unpersuasive reasoning, has reached a contrary result. See In re Kielhafner, 639 S.W.2d 115 (Mo.Ct.App.1982) (‘‘[T]he facts here establish that any liability of defendants for late closing was discharged by the execution and delivery of the deeds and the receipt by the estate of the purchase price specified in the contract.”). Kielhafner represents a particularly harsh application of the merger doctrine, especially since the plaintiff there made "repeated protestations ... that the defendants were unreasonably delaying closing,” and even requested, at the time of closing, "that defendants pay interest for the period of delay." Id. at 117. The court was unimpressed with these efforts, because the plaintiff did not attempt to terminate the contract based on delay, or to "insist upon a provision in the deeds holding open the payment of interest for late closing.” Id. at 118. But such a rule renders a time of performance clause practically nugatory; unless the vendee sues before tardy delivery is effected, the vendor can violate the clause with impunity merely by tendering the deed, forcing the vendee either to reject the deed and litigate, or to accept the deed and forfeit the claim for violation of the clause.
. In that regard, appellants note that in Virginia once a court sitting in equity obtains jurisdiction over a case, that court can provide a legal remedy, even if the equitable remedy becomes moot by later events, such as voluntary performance. See Turney v. Smith, 211 Va. 810, 814, 180 S.E.2d 509 (1971); Grubb v. Sharkey, 90 Va. 831, 834, 20 S.E. 784 (1894); Nagle v. Newton, 63 (22 Grat.) Va. 814, 821 (1872).
. See Lawrence Berger, Merger by Deed— What Provisions of a Contract for the Sale of Land Survive the Closing?, 21 Real Est. L.J. 22, 63 (1992) ("On the point of merger, it would seem that the [late closing], though clearly deed-related, has resulted in performance at a time beyond that set by the contract, and thus it should be assumed that the buyer would not ordinarily intend to give up the right to damages by accepting the later performance.”); Parnell, supra note 4, § 13 (1954) ("While the decisions are not numerous, most courts discussing the question appear to have taken the view that an express stipulation as to time of conveyance or possession is not merged in a deed accepted by the vendee and containing no provisions in this respect, particularly where it is shown that time was a primary factor inducing the agreement.”); 77 Am.Jur.2d Vendor & Purchaser § 290 (1997) ("A stipulation in a contract for the sale of real estate, to deliver a deed at a specified time upon a contingency fully performed, does not necessarily merge in a subsequently delivered and accepted deed.”); 92 C.J.S., Vendor & Purchaser § 576(d) (1955) ("Execution and acceptance of a deed at a time subsequent to that fixed for that purpose by the sale contract entitle the purchaser to sue for the damages from delay arising from the breach of the provision as to the time of conveyance; in such a case, the acceptance of the deed when it is tendered does not preclude the action.”).
. See Miller v. Kemp, 157 Va. 178, 160 S.E. 203 (1931) ("Why should any one be required to look behind the recorded title and run down the preliminary contracts to discover that the parties to a solemn deed have made a mistake?”) (quoting Donaldson v. Levine, 93 Va. 472, 25 S.E. 541); cf. 6 Corbin, supra,
. See Miller v. Kemp, 157 Va. at 201, 160 S.E. at 210 (holding that deviation between the deed and the original contract reflected "a change in [the parties) original agreement”); 5C Michie’s Jurisprudence, Deeds, supra, § 107 ("Insofar as a deed varies from a prior executory contract pursuant to which it is executed, such departure is presumed to represent a change mutually agreed upon by the parties before its execution....”).