DocketNumber: No. 5704
Judges: Crow
Filed Date: 9/9/1905
Status: Precedential
Modified Date: 10/19/2024
On April 2, 1902, E. M. Henningsen and Tliorvald Olsen, copartners under the firm name and style
Under the provisions of the act of Congress of August 13, 1894, chapter 280, 28 Stat. 278, the United States government required, and the said contractors furnished, a penal bond in the sum of $20,000, executed by appellant, the Aetna Indemnity Company, as surety, conditioned that said Henningsen & Co. should fully perform said contract and promptly make payments to all persons supplying them with labor and materials in the prosecution of the work therein provided for. Said Henningsen & Co., in the performance of said contract, purchased from respondent, the Standard Furniture Company, certain furniture called for in said stipulations, to the total value of $693, on which they made a partial payment of $400. Ho further payment being made, this action against said Henningsen & Co. and appellant, the Aetna Indemnity Company, was brought on said bond, to recover $293 remaining due. Appellant, the Aetna Indemnity Company, in its answer, pleaded the following affirmative defenses:
“(1) For a first further and affirmative defense, this der fendant alleges that the goods, wares, and merchandise alleged to have been furnished by the plaintiff were not such goods and merchandise as went into the construction of the buildings, and were not labor and material, within the meaning of the statute, as would entitle this action to be brought in the name of the United States.
“(2) For a second and further affirmative defense, this defendant alleges that the goods, wares, and merchandise alleged to have been furnished to the defendant, B. M. Hen*90 ningsen & Co., were furnished on or about the 17th day of April, 1903, and that the time for payment thereof by the defendant, R. M. Henningsen & Co., was extended without the knowledge or consent of this surety, and to its detriment.”
To these defenses, respondent interposed separate demurrers, which the court overruled as to the first but sustained as to the second. Respondent by its reply denied the allegations of said first affirmative defense. Upon trial, findings of fact and conclusions of law were made, and judgment was entered thereon in favor of respondent. From said judgment, this appeal has been taken.
.Appellant’s first contention is that the materials furnished, being personal property and not having entered into the permanent structures) were not such materials as would give plaintiff a right of action in the name of the United States, under said act of Congress, on the bond in question; and that the trial court therefore erred in refusing to grant apr pellants motion to- dismiss, made at the opening of the case, upon the ground that the complaint did not state facts sufficient to constitute a cause of action; and also erred in refusing a nonsuit. Appellant, in support of the proposition, urges that the object of the act of August 13, 1894, 28 Stat. 278, was to give the same relief by a proceeding upon the bond of a public contractor that -could be had by foreclosure of a mechanic’s or materialman’s lien on a building erected by a private owner, claiming such purpose to have been the evident intent of Congress, and that said statute should receive such construction at the hands of the court. Appellant has cited numerous- authorities for the purpose of sustaining its contention that this statute was intended to afford relief to such parties as would ordinarily be entitled to- a mechanic’s or materialman’s lien under statutes of the various states, were the buildings private instead of public. There is no question but that said statute affords such relief to the subcontractors, laborers, and materialmen;
“That hereafter any person or persons entering’ into a formal contract with the United States for the construction of any public building, or the prosecution and completion of any public work or for repairs upon any public building or public work, shall be required before commencing such work to execute the usual penal bond, with good and sufficient sureties, with the additional obligations that such contractor or contractors shall promptly malee payments to all persons supplying him or them labor and materials in the prosecution of the work provided for in such contract; and any person or persons making application therefor, and furnishing affidavit to the Department under the direction of which said work is being, or has been, prosecuted, that labor or materials for the prosecution of such work has been supplied by him or them, and payment for which has not been made, shall be furnished with a certified copy of said contract and bond, upon which said person or persons supplying such labor and materials shall have a right of action, and shall be authorized to bring suit in the name of the United States for his or their use and benefit against said contractor and sureties and to prosecute the same to final judgment and execution; Provided, That such action and its prosecutions shall involve the United States in no expense.” 28 Stat. 278, c. 280, § 1.
This act should be liberally construed, and from its wording we are of the opinion that, not only are claims of the character suggested by the appellant protected by the bond therein mentioned, but persons furnishing any materials in the prosecution of the work provided for are also protected thereby, even though such' materials do not enter into, or become a part of, any permanent structure. The United States circuit court for the district of Maine, in American Surety Co. v. Lawrenceville Cement Co., 110 Fed. 717, at page 719, says:
“In using the expression which we have quoted from the statute and the bond, there can be no question that Congress had somewhat in mind statutes in various states giv*92 ing liens on buildings and other property, real and personal, for labor and material. Nevertheless, this statute does not have the same aspect as the ordinary lien statutes referred to, and therefore the latter can afford only very general assistance with reference to the construction of the former. The ordinary lien statutes have been justly and strictly held to cover only what has added to the value of the property against which the lien is asserted, and therefore they are ordinarily administered to protect only what is actually incorporated into its substance. . . . The underlying equity of the lien statutes relates to a direct addition to the substance of the subject-matter of the building, or other thing, to which the lien attaches, while the statute in question concerns every approximate relation of the contractor to that which he has contracted to do. Plainly, the act of Congress and the bond in the case at bar are susceptible of a more liberal construction than the lien statutes referred to, and they should receive it. In the one case, as in the other, the dealings of the person who claims the statutory security must approximate the work, and in the one case as well as in the other there must be • a certain margin within which there will be difficulties in discriminating between what is and what is not protected. Nevertheless, we are not concluded by the decisions with reference to the ordinary state statutory liens. We can apply them only in a general way, and we are not so restricted by them as to require a construction inconsistent with the remedial purposes of the statute now in issue.”
See, also, United States to Use of Tidewater Steel Co. v. Perth Amboy Shipbuilding etc. Co., 137 Fed. 689. Under the construction given to said act by the above 'authorities, which we feel obliged to follow, there can be no question but that respondent was entitled to recover on said bond for the furniture which it sold to said contractors in pursuance of the terms and stipulations of said contract.
But were it to be conceded that said furniture was not contemplated by the statute, it was clearly required by the contract, being a part of its subject-matter. The bond was given to secure the faithful performance of said contract and payment to all parties furnishing any material there
“Waiving, however, the general character of this last reason, we will for a moment consider the point made under it, that the act of Congress (Act Aug. 13, 1894, c. 280, § 1, 28 Stat. 278 [U. S. Comp. St. 1901, p. 2523]) gives a right of action only to persons supplying labor and materials ‘for the construction, of any public building, or the prosecution and completion of any public work, or for repairs upon any public building, or public work,’ which provision does not include steamers for the harbor service of the quartermaster’s department; and counsel cites in support of his proposition definitions of ‘public works’ from the Century Dictionary and the Am. & Eng. Ency. of Law (2d ed.). Without quarreling with these definitions, we conclude that the meaning of the words ‘public work’ in the act is broader and more comprehensive than the dictionary meaning given to ‘public works’; that public work is susceptible of application to any constructive work of a public character, and is not limited to fixed works. The statute should be liberally construed to accomplish its purpose. But without further discussion of the point, it is quite sufficient to say that, whether the foregoing view is correct or not, the defendants are estopped from setting up such defense; they executed the bond well knowing its intent and purpose, and, since the purpose was not immoral or illegal, they cannot now be heard to deny their liability, voluntarily assumed and undertaken.”
We are satisfied that the recovery had by respondents in this action was contemplated by said statute and also by said bond.
Appellant further contends that the court erred in sus
We find no prejudicial error in the record. The judgment is affirmed.
Mount, O. J., Hadley, Fullerton, and Dunbar, JJ., concur.
Hoot, J., having been of counsel, took no part.