DocketNumber: No. 24185. En Banc.
Citation Numbers: 22 P.2d 984, 173 Wash. 294, 1933 Wash. LEXIS 625
Judges: Mitchell
Filed Date: 6/14/1933
Status: Precedential
Modified Date: 10/19/2024
H.E. Nelson entered into a contract with the city of Tacoma, on August 12, 1931, to perform *Page 295 the work and furnish all labor, tools, materials, equipment and supplies in cleaning and painting a stand pipe belonging to the city, the contract price being $2,211. At the same time, he executed and delivered to the city his bond, as contractor, for the performance of the work and as security for the payment of laborers, mechanics, materialmen, etc., as required by Rem. Rev. Stat., § 1159, with the Indemnity Insurance Company of North America as surety. Two days later, the contractor executed and delivered to W.P. Fuller Co. (who will be hereinafter spoken of as Fuller Co.) a written assignment of any and all moneys due or to become due to him under the contract. The assignment was filed with the controller of the city, but it was not accepted by the city or any of its officers.
On the faith of the assignment, Fuller Co. furnished the contractor $2,045 in money, which it appears was used by the contractor in the performance of the work. Fuller Co. filed a claim for this item, and also filed a claim in the sum of $376.85 for material furnished to be used, and which was used, in the performance of the contract. Eight other claims for labor and material furnished were filed in the sum of $939.18.
The contract was fully performed, and the work accepted by the city. The time for filing claims expired. The city had paid no part of the contract price. The surety company, to lessen or protect its liability on its bond, then brought this action against the contractor, the city and all the claimants, to recover a judgment requiring the payment of claims for labor and material out of the funds owing by the city, in preference to any right of Fuller Co. under the contractor's written assignment upon which Fuller Co.'s claim of $2,045 was made. Issues were made up between *Page 296 the parties. At the trial, the city, by directions of the court, paid the whole contract price into court, to be distributed according to directions in the judgment to be entered.
A judgment was entered allowing a small premium to the industrial insurance department, and allowing all claims for labor and material, including Fuller Co.'s claim in the sum of $376.85, to which no one objects, except Fuller Co., who contends that its claim for $2,045 should be preferred over all claims for labor and material. To the extent of that adverse decision, Fuller Co. has appealed.
[1] The contract provides that the contractor shall not, either legally or equitably, assign any of the moneys payable under the contract, or his claims thereto, unless with the consent of the city. This is a plain, important provision of the contract, which was known to Fuller Co. when it took the assignment. To permit Fuller Co. to recover its so-called superior or preferred claim of $2,045, nearly equal to the total amount of the contract price, would render nugatory the specific prohibition in the contract against the assignment of moneys due under it; thus necessarily, though indirectly, resulting to the detriment of a contract upon which there is a surety, as required by statute, for the performance of a contract which specifically provides against assignment of moneys due under the contract.
Still further, we are persuaded to reach the same conclusion because of the last clause or sentence in Rem. Rev. Stat., § 1159, providing for a bond with surety to perform the public works contract and to "pay all laborers, mechanics and sub-contractors and materialmen," etc., which last clause or sentence is as follows: *Page 297
"Provided, however, that the provisions of this act shall not apply to any money loaned or advanced to any such contractor, subcontractor or other person in the performance of any such work."
The purpose and intent of that statute would be destroyed if, in a case like this, one against whom the provision runs were allowed to take practically all of the funds derived from the performance of the contract.
Appellant cites and relies on Hall Olswang v. AetnaCasualty Surety Co.,
That portion of the opinion in Fidelity Deposit Co. v.Auburn,
The assignment in the case of National Surety Co. v. AmericanSavings Bank Trust Co.,
The case of Northwestern National Bank v. Guardian *Page 298 Casualty Guaranty Co.,
Authorities from other jurisdictions cited by appellant are not applicable to this case, in our opinion.
The claimants who furnished labor and material which was used in the public work were entitled to preference over the appellant out of the funds deposited in court by the city. That was the judgment of the superior court.
Judgment affirmed.
BEALS, C.J., MAIN, TOLMAN, HOLCOMB, MILLARD, STEINERT, and BLAKE, JJ., concur. *Page 299
Hall & Olswang v. Aetna Casualty & Surety Co. , 161 Wash. 38 ( 1931 )
National Surety Co. v. American Savings Bank & Trust Co. , 101 Wash. 213 ( 1918 )
Northwestern National Bank v. Guardian Casualty & Guaranty ... , 93 Wash. 635 ( 1916 )
Fidelity & Deposit Co. of Maryland v. City of Auburn , 150 Wash. 114 ( 1928 )