The plaintiffs, Cunningham, Nelson and Trezise, commenced separate actions in the superior court for King county, seeking recovery of damages for the alleged unwarranted cancellation by the directors of defendant school district of contracts separately entered into by the plaintiffs with the district for the transportation of students from their homes to the high school of the district. The cases being determinable upon facts, which are to a large extent applicable to each, they were, by stipulation of counsel for all parties, consolidated for the purpose of trial
The defendant is a rural high school district of King county. From June, 1921, to June, 1922, the members of the board of directors of the district were Albert Prenatt, C. H. Nelson, father of plaintiff W. E. Nelson, and E. "W. Trezise, father of plaintiff Gordon T. Trezise. It is conceded that, because of the territorial extent of the district, it was necessary that there be provided, at the expense of the district, transportation for a considerable number of its students from their homes in different portions of the district to its high school. Early in September, 1921, at the beginning of the school year, these directors, acting for the school district, entered into separate contracts with the plaintiffs for the transportation by them of students from their homes to the high school from different portions of the district for the term of two years, each of the plaintiffs to furnish and maintain his own conveyance for that purpose, the district to pay each a stipulated monthly compensation therefor.
A short time thereafter, and after the commencement of the performance of the services agreed upon, some question arose as to the legality of the contracts between the district and the plaintiffs Nelson and Trezise, because of the fact of those contracts being awarded to sons of two of the directors, and also because of the fact that, in the performance- of those contracts, the plaintiffs Nelson and Trezise were using automobiles belonging to their fathers, members of the school
On September 1,1922, the personnel of the board of directors having changed, they assumed to cancel and hold for naught these three contracts, which, according to their terms, were to continue for another year, and employed others to furnish the transportation which, according to the terms of the plaintiffs’ contracts, they were entitled to perform, and notified the plaintiffs accordingly. The plaintiffs protested against such cancellation and each continued to offer his services to the district and demand compensation therefor, as he conceived to be his right under the terms of his contract. No question is here made as to the amount of damages suffered by each of the plaintiffs and awarded by the trial court, if they are entitled to any recovery at all. Therefore, we do not notice the amounts involved or awarded.
The principal contention here made by counsel for the district with reference to the Nelson and Trezise contracts, is that those contracts were illegal and voidable because of the alleged fact that the directors
As to the charge of fraud with reference to the contract with Cunningham, we see no substantial support whatever for the contention that the conclusion of the trial judge was wrong.
In its last analysis, there is nothing involved in this controversy other than questions of fact. In view of our conclusion with reference to these principal contentions, we find it unnecessary to notice the claims made by the district by its cross-complaints for refund of amounts paid to the plaintiffs on their contracts. We think a further discussion of the case would serve no useful purpose.
The judgments are affirmed.
Main, C. J., Holcomb, and Tolman, JJ., concur.