DocketNumber: No. 4403
Citation Numbers: 31 Wash. 320, 71 P. 1016, 1903 Wash. LEXIS 629
Judges: Mount
Filed Date: 3/19/1903
Status: Precedential
Modified Date: 10/19/2024
Tlie opinion of the court was delivered by
— This is an action to foreclose a mechanic’s lien. Findings and a decree were made in the court below in favor of the plaintiff for the sum of $3,260.15, with interest from February 8, 1900, for attorney’s fees and costs. From this decree the defendant appeals.
The facts are substantially as follows: On August 31, 1899, the respondent entered into a contract with the
“It is hereby agreed between said parties that the original contract shall be in full force and effect until the entire contract is completed, and that this instrument shall be a part and parcel of said contract. Said party of the first part hereby agrees and promises: (1) To stop all brick work on said building immediately; (2) to take proper care of all materials now upon the premises and which are yet to be delivered; (3) to protect all portions of the work effectually against the action of the elements, as directed by the superintendent; (4) to commence the work within three days after receiving written notice from the superintendent; (5) to waive all claims for additional compensation on account of suspension of work; (6) to keep the surety bond in force until the contract is completed. Said parties of the second part hereby agree: (1) To pay for the following materials: For 80,081 feet of lumber now on the premises, $720; for iron work now on the premises, $245; for mill work, $200; 33,786 feet of lumber yet to be delivered, $274.07; 175,000 brick, $1,268.75. 85 per cent, to be paid every two weeks on brick delivered; balance of 15 per cent, thirty days*323 after all the brick have been delivered. 78,000 feet seasoned flooring $936, to be paid for in six weeks. (2) To extend the time for completion of the building to June 1, 1900.”
This contract did not call for a cessation of work on the building, and respondent kept men at work on the inside thereof doing carpenter work, and also kept teams hauling material. Thereafter, on January 2, 1900, an estimate of labor and materials, amounting to $2,230, was made by the superintendent, and given to respondent. This estimiate was not paid when it was presented to the Spaulding Company, but was subsequently paid on June 29, 1900. On February 8, 1900, another estimate for $282 was made, and given to respondent, which estimate has not yet been paid. The total amount paid to respondent upon the contract is $12,632. When the certificate of estimate above named, for $2,230, was presented to the Spaulding Company for payment, the respondent was informed that the company was insolvent, had no money, and could not pay the estimate. Several conferences were had thereafter between respondent and the Spaulding Company and the superintending architect. The result of these conferences was that the respondent notified the Spaulding Company and the superintendent that, unless the amount due were paid, he could not finish the building, and that the contract would be void. This was assented to by the Spaulding Company, and on February 28, 1900, all work was stopped on the building. Subsequently, on the 18th day of April, 1900, the claim of lien sought to be foreclosed in this action was filed against the property for $4,200. On the 13th day of April, 1900, the Spaulding Company agreed to sell all their interest in the uncompleted building to the appellant, and on the 26th of April duly assigned the contract with the respondent to
It is argued by appellant that the respondent was in duty bound to finish the building under the terms of the contract, and that, upon his refusal to do- so- after notice by appellant, appellant was at liberty to proceed under the terms of the contract, finish the building in accordance with the plans and specifications, and charge the same up to the contractor, and account to him only for the balance due, after deducting the cost thereof, and payments already made from the contract price. This argument is based on tbe assumption that the contract between appellant and respondent was still in force after assignment by the Spaulding Company. We think the evidence in this case clearly shows that prior to the assignment the contract between respondent and the Spaulding Company had been rescinded and abandoned by mutual consent of the Spaulding Company and respondent, and therefore that respondent was not hound to proceed with the
The question to be determined, then, is what amount was due the respondent upon the work done at the time the contract was rescinded. It is contended by appellant that the amount found due by the lower court was based upon the quantum, meruit, and not upon the contract price of the labor and material already in the building. The superintending architect testified that on February 8, 1900, he made an estimate of all the work done and materials furnished and put into the building, and that “the reasonable value thereof according to the contract price was $15,193that in addition to- this sum there was an item of $389.28 for extras, and $245 for iron work on the premises, and $65, the agreed price of a platform which had not been included in his estimates; making a total of $15,892.28. We think this evidence is sufficient to show that the estimate of the work done was according to the contract price, even if the rule- is as is contended for by the appellant, viz., that the amount of his recovery must be based upon the contract price of the labor and materials actually in the building at the time the contract was rescinded. There is no other evidence in the record tending to show that the work was of less value than the estimate made by the superintending architect above quoted, except that there was evidence to the effect that the price of labor and materials had increased in value at the time the respondent ceased work. But this fact does not aid appellant, because the estimates were not based on this increase of price, but
Appellant also contends that interest should not have been allowed from February 8, 1900. In this, we think, the appellant is correct. In the lien notice no claim was made for interest. In the complaint no claim was made for interest prior to- April 18, 1900, the date of the filing of the lien. Where no claim is made for interest by the lien notice prior to the date thereof, and where the prayer of the complaint is for interest from the date of the lien, we think interest should not be allowed prior to that date.
The decree will be modified to- this extent: that interest at the legal rate will he allowed on the amount found due, viz., $3,260.15, from April 18, 1900. In all other respects the decree is affirmed; neither party to recover costs on this appeal.
Fullerton, C. J., and Anders and Dunbar, JJ., concur.