DocketNumber: No. 8767
Citation Numbers: 61 Wash. 167, 1910 Wash. LEXIS 1306, 112 P. 88
Judges: Gose
Filed Date: 12/12/1910
Status: Precedential
Modified Date: 10/19/2024
This is a bill in equity for the foreclosure of a mechanics’ lien. On August 26, 1908, the respondent entered into a building contract with the appellant, Olaf Nelson, acting through one Anderson as his attorney in fact. By the terms of the contract the respondent agreed to erect for the appellant, Nelson, hereafter called the appellant, a two-story frame building consisting of twelve flats, six of five rooms each, and six of four rooms each. Respondent agreed to fur
The appellant first contends that the building as constructed is only 110 feet in length instead of 11£ feet, as the contract requires. Upon this feature of the case the court found:
“The defendant contended in this action that the building constructed by the plaintiff was from eighteen inches to two feet shorter than required by the contract. I find from a preponderance of evidence that at the time the plaintiff was ready to commence the construction of said building the dimensions of the building were made the subject of discussion between the plaintiff and the agent and attorney in fact of the defendant and that under an agreement then entered into a ground dimension slightly shorter than the length of the lot was determined on, but that the cornice and bay windows of said building practically reached to the limits of said lot, and that it was constructed upon a plan satisfactory to the defendant to avoid any possible controversy with the building inspector of the city of Seattle.”
We think the finding is supported by the evidence. The respondent testified that the lot was represented to him to be 114 feet in length, but that when measured it was found to have a length of 112 feet; that he had had trouble with the city inspectors when attempting to put the cornice and windows of other buildings over the street, and that he so
It is next insisted that the building was not completed within the time fixed by the contract, and that the appellant should have been allowed an offset in damages. The court found:
“It was contended by the defendant that the building was not ready for occupancy on December 15, 1908, the time fixed in the contract, but the court finds that there is no competent evidence that the defendant sustained any damage by reason thereof, and that the delay in that behalf was due largely to the inclemency of the weather.”
The respondent testified that the building was ready for occupancy on December 15, the date fixed for its completion, and that the appellant took possession January 22 following.
Damages, in legal acceptation, mean compensation for the loss suffered or the injury sustained. The flats were built for renting. There is no evidence that there were any applications for rooms before the completion and delivery of the building. Damages will not be awarded unless they are based on something more substantial than guess, assumption, or speculation. McCarthy v. Gallagher, 4 Misc. Rep. 188, 23 N. Y. Supp. 884. Interest was allowed only from February 15, 1909, the date of the filing of the lien. This, we think, afforded the appellant ample compensation for the delay, if any, in the completion of the building.
Finally, it is said that the motion for a new trial was heard and decided in Pierce county, and that this was error. The record shows that the motion was denied in King county in open court. Accepting, however, the statement of counsel for the appellant, it was error without prejudice. The case is tried here, de novo. The motion for a new trial was properly denied. Shaw v. Spencer, 57 Wash. 587, 107 Pac. 383.
The j udgment is affirmed.
Rudkin, C. J., Fullerton, Parker, and Mount, JJ., concur.