DocketNumber: No. 11362
Citation Numbers: 77 Wash. 70, 137 P. 342, 1913 Wash. LEXIS 1898
Judges: Ellis
Filed Date: 12/26/1913
Status: Precedential
Modified Date: 10/19/2024
The plaintiffs in this action seek to establish liens upon the irrigating canal of the defendant Yakima Valley Canal Company, for labor performed by them for the defendant Betts in screening sand and gravel used by defendant Powell in reconstructing the canal.
The facts are simple and practically undisputed. The defendant W. F. Powell entered into a written contract with the defendant canal company to reconstruct approximately 11,-000 feet of its canal, according to certain plans and specifications, and at his owp cost and expense, to perform all the work and furnish all the materials called for in the specifications, excepting the reinforcing steel. The work called for in the specifications was the excavation and grading of the foundations for the flume, and the construction of a reinforced concrete flume thereon, and, at one point, a concrete siphon. The defendant canal company owned the right of way upon which the canal was reconstructed. The work was done, and materials used were cement, sand, gravel and steel. The sand, gravel and cement were mixed together and, with the reinforcing steel, constituted the finished structure.
The evidence is too plain for controversy that the defendant W. C. Betts made an oral agreement with Powell to furnish sand and gravel at an agreed price of sixty-five cents a yard. Betts had his own screening machinery and sand and gravel bins, and was to deliver the materials in his own bins, from which Powell was to haul them to the place of construction. Betts set up his machinery at a certain sand bar, in the Natchez river, at a point about two hundred yards from the nearest point of the canal right of way, and about one-fourth of a mile from the place where the work of reconstruction was in progress. The plaintiffs were employed by Betts in scraping up, screening, and separating the sand and gravel, storing these materials- in the bins, and in' running
Judgments by default were entered against the defendant W. C. Betts for the amounts due to the plaintiffs, the action was dismissed as to the defendant Powell, and a decree was entered establishing and foreclosing liens
The respondents contend that W. C. Betts was a subcontractor, and as such, the statutory agent of the canal company in employing the laborers who screened the sand and gravel. The appellant insists that Betts was a materialman and had no part in the actual construction of the canal, and hence there was no basis in the facts for a statutory agency.
The statute under which these liens were claimed, Rem. &
“Every person performing labor upon or furnishing material to be used in the construction, alteration or repair of any . . . ditch, dyke, flume ... or any other structure . . . has a lien upon the same for the labor performed or material furnished' by each, respectively, whether performed or furnished at the instance of the owner of the property subject to the lien or his agent; and every contractor, subcontractor, architect, builder or person having charge, of the construction, alteration or repair of any property subject to the lien as aforesaid, shall be held to be the agent of the owner for the purposes of the establishment of the lien created by this chapter.”
An analysis of this section, as it seems to us, clearly sustains the appellant’s contention. The lien for labor is accorded for work performed upon the ditch or flume, and at the instance of the owner or his agent. No lien is accorded for labor performed in the preparation of materials being furnished by the materialman, and at the instance of the material-man. This seems plain from the language of the first clause of the section. All doubt, if there could be any, is removed by the next clause of the same section, which makes only the contractor, subcontractor, architect, builder, or person having charge of the construction, the agent of the owner for the purpose of establishing the lien. The statutory agency is confined to the persons named. A materialman is not one of them.
Betts employed all of the respondents. According to their own testimony, they performed labor for him alone. There was not a glimmer of evidence that the respondents did any work at the request of any one else. Neither of the respondents testified that he was employed by, or looked to either the canal company or to Powell for his pay. Neither Betts nor any of his employees had any part in the actual work of constructing the canal. Betts was clearly a materialman. Finlay v. Tagholm, 62 Wash. 341, 113 Pac. 1083. He was not
“A subcontractor is one who takes from the principal contractor a specific part of the work, and the term does not include laborers or materialmen. Farmers’ Loan & Trust Co. v. Canada & St. Louis R. Co., 127 Ind. 250, 26 N. E. 784, 11 L. R. A. 740.” Young Men’s Christian Ass’n v. Gibson, 58 Wash. 307, 105 Pac. 766.
Betts merely furnished the sand and gravel used in the work, just as some one else furnished the cement, and still another the steel. If he was a subcontractor, then every materialman would fall within that class, and the distinction manifestly intended by the statute would be obliterated. He was not a statutory agent of the owner by any construction of the statute, however liberal. To hold that he was, would be to legislate, not to construe.
“If one who furnishes the sashes, doors, and glass for a building is a subcontractor, every materialman would fall in that class, and such construction would nullify the plain terms of the statute. The argument that the contract to furnish the material is an entirety and that it is difficult to comply with the statute, is one that should be addressed to another department of the state government. We are not responsible for the wisdom or the expediency of the law.” Finlay v. Tagholm, 62 Wash. 341,113 Pac. 1083.
See, also, Monroe v. Clark, 107 Me. 184, 77 Atl. 696, 30 L. R. A. (N. S.) 82. The statute makes, and preserves throughout, a distinction between materialmen and subcontractors. It accords a lien to both, but upon different conditions. The materialman must, within five days after the first delivery of materials, deliver or mail to the owner of the property a notice in writing that he is furnishing the materials. Laws of 1911, p. 876 (8 Rem. & Bal. Code, § 1188). It was testified and tacitly admitted that no such notice was delivered or mailed in this instance.
Even if it could be held that the laborers employed by
The respondents assert that the screening apparatus was placed at Powell’s direction where it was most serviceable, relative to the balance of the work. No citation to the record in support of this statement is made, and a careful reading of the record fails to disclose any such testimony. In any event, that circumstance would be immaterial. The apparatus was doubtless located with a view to the convenience of all of the parties concerned.
The respondents further contend that, the trial court having found that Betts was a subcontractor, and the question involved being not one of law but of fact, this court is not at liberty to disturb that finding. This contention is erroneous for two reasons. In the first place, on undisputed evidence as to the facts, whether the lien arose or not was a question of law. In the second place, this is a trial de novo, in which the findings of the trial court, though entitled to weight, have no binding force upon us. Johns v. Arizona Fire Ins. Co., 76 Wash. 349, 136 Pac. 120, and cases there cited. Borde v.
Respondents cite decisions from other jurisdictions to the effect that, in order to have a lien for labor, it is not necessary that the labor be performed on the premises where the improvements are actually made. This is, of course, true if the labor was performed directly for the owner, or for the principal contractor, or for his subcontractor, who has undertaken to perform some specific part of the work of actual construction. The cases cited go no further. In Evans Marble Co. v. International Trust Co., 101 Md. 210, 60 Atl. 667, 109 Am. St. 568, a subcontractor, by contract with the principal contractor, agreed to carve, erect, place, and finish all the exterior marble work on a certain structure. The statute there under discussion gave a lien for labor only. The subcontractor who directed all of the work of preparing and placing the marble in the structure was accorded a lien for his labor. The right to a lien in favor of laborers employed by him was not involved nor discussed. In Scannell v. Hub Brewing Co., 178 Mass. 288, 59 N. E. 628, it was merely held that a lien could be maintained for labor performed under an agreement with the property owner to furnish and erect brewery boilers set up in brick work, with all pipe connections, and also certain tank work. Part of the work was done at the petitioner’s works in preparing the material. The lien was claimed by, and allowed to, the original contractors for preparing and setting up the boilers. As in the last case cited, no right of lien as in favor of the claimant’s employees was either involved or discussed. In Daley v. Legate, 169 Mass. 257, 47 N. E. 1013, it was held: that workmen were entitled to a lien for labor on materials which they knew were
Finally, we say that, since the statute clearly contemplates a distinction between subcontractors and materialmen, the line of distinction contemplated by the statute between these two must be definitely drawn somewhere, otherwise the owner of property would never know how to protect himself. He would never know when or where even to seek the information necessary to protect himself. He can reasonably be expected to know of a subcontract, and the work performed in carrying it out, because the work of the subcontractor, or some part of it, is performed upon the property, and in the actual construction of the improvement. It would be wholly unreasonable to expect him to go afield and investigate as to all labor performed by employees of materialmen furnishing the various materials used in the work, none of such labor being
The decree foreclosing the alleged liens is reversed, and the cause is remanded for dismissal as to the appellant canal company.
Ceow, C. J., Main, Chadwick, and Gose, JJ., concur.