Judges: Fairchild
Filed Date: 1/10/1956
Status: Precedential
Modified Date: 11/16/2024
As far as the result in this appeal is concerned, it must be based on the legal character of the contract entered into by respondent with appellant and its obligation.
Appellant contends that the principal issue in this case is whether the defect in the barn was caused by defective workmanship, and that therefore findings should have been made, among others, that the “sagging roof, bulging walls, and other defective conditions were due to respondent’s failure to perform his vrork as a carpenter in a good and workmanlike manner,” and that “the plaintiff failed to exercise the skill and ability which respondent represented that he possessed.”
With respect to the quality of the lumber, Lyle Richmond, one of the workmen, testified that “Mr. Lind objected to certain material. The nature of the objection was that I threw away a lot of boards that I didn’t think were fit for rafters at first, but we had to use those anyway before we were done.” Mr. Lind testified to the same effect that “There was some poor lumber used, here and there and all over, in the roof boards and some of it in the last rafters we made. Toward the last end he had a lot of punky lumber. It was rotten, punky elm lumber, drop a hammer on it and it would go right through.” As to the rafters, the appellant admitted that “Lind wanted to put the rafters three feet apart, but I said, ‘No, we can’t put them three feet apart. I have eight-foot lumber. I will waste too much.’ Then he said four feet.” With respect to the beams, the testimony of Martin Lind was that when the driveway was being cut he asked appellant for 2 x 4 24-foot beams, but Allen refused on the ground that he couldn’t afford it.
If the sagging of the barn arose from any of the above sources or a combination of them, the fault can be attributed only to the appellant, who planned the barn and insisted on the carrying out of his plans in accordance with the materials which he had on hand. The evidence shows that the appellant was present at various and numerous times during the construction of the building. He testified: “I was present while the barn was being constructed one week and maybe two or
The respondent’s claim is for compensation for work and services under a master-and-servant relationship. No length of time was fixed. Either party could sever the relation at any time, and the arrangement of hire contained no warranty as claimed by appellant. The testimony shows that the status of the respondent was that of a carpenter working for the appellant at the rate of $1.25 per hour. The following testimony was given by the appellant Allen:
“Q. He was working by the hour for you? A. Yes, that is the way they got paid.
“Q. And you could have left him go any time you wanted to? A. Yes.
“Q. But you didn’t? A. No.”
Respondent’s duty was to perform the task he was hired to do, and under the facts established that duty cannot be enlarged into a guarantee that he would construct a roof without a sag. Appellant has failed to point out any instance of poor workmanship on the part of respondent. The appellant selected the plan, directed the work, and furnished the materials. He cannot recover for a defect in the barn for which respondent is not responsible.
The trial court found, among other things, that the respondent was hired “to do carpenter work in the construction of a barn upon the defendant’s premises ... at the rate of $1.25 per hour and the defendant hired other workmen who
As there was no warranty, the cause of the sag and the requested findings pertaining thereto were immaterial to the determination of the case. It appearing that it was not probable that the substantial rights of the appellant have been affected, the order was properly denied, and the judgment must be affirmed.
By the Court. — Judgment and order affirmed.