DocketNumber: 5712
Citation Numbers: 137 S.E. 356, 103 W. Va. 318, 1927 W. Va. LEXIS 62
Judges: Lively
Filed Date: 3/8/1927
Status: Precedential
Modified Date: 10/19/2024
The validity of a materialman's lien is here involved.
The Charleston Baptist Church through its Trustees, Thomas J. Mason and others, contracted the erection of its church with Ring-Hartman Company, a corporation, which gave bond with defendant, Standard Accident Insurance Company as surety for the faithful performance of the contract and to indemnify against mechanics and materialman's liens. Later Pfaff Smith Builders Supply Company instituted this suit in the Court of Common Pleas to enforce its materialman's lien, and Metal Products Company, appellant herein, came into the suit by petition to enforce its lien for specially fabricated steel trench covers furnished the contractor, and the validity of that lien is here involved. It amounts to $444.78, including interest at date of decree. The decree appealed from, entered July 13, 1926, denied the claim as a lien upon the church property, and required appellant *Page 320 to pay a proportion of the costs. By order of April 5, 1926, the Circuit Court refused the appeal, being of the opinion the decree of the Court of Common Pleas was plainly right.
The answer of Standard Accident Insurance Company charges that Metal Products Company's purported lien is invalid; that petitioner failed to perfect its alleged lien; that its notice of lien filed in the County Clerk's office is wholly insufficient under the statute, as set out in sub-section (b) of Sec. 3, chap. 75 of the Code.
The cause was referred to a Master Commissioner who reported petitioner's claim as a valid lien, to which report exceptions were taken by Standard Accident Insurance Company, and the Court sustained the exceptions. The exceptions are: (1) That said lien was not perfected because no proper notice thereof was recorded in the County Clerk's office; and because the notice thereof filed in said Clerk's office and not recorded is insufficient under the statute; and (2) That the evidence before the Commissioner shows that the material forming the basis of the lien were never used in the building and never became a part thereof. These exceptions thus sustained, formed the issues, and both were decided against appellant.
Was the lien of appellant perfected as required by the statute?
It appears that appellant is a corporation, and on January 28, 1924, proposed to the Ring-Hartman Company to furnish the trench covers for $420.00 for use in the Baptist Temple Building, which proposal was accepted by Ring-Hartman Company, the general contractor. The trench covers were fabricated in accordance with the plan for the building and were delivered, according to petitioner, inside the building on June 26, 1924. On August 21, 1924, notice was served upon the trustees that certain materials in the nature of steel and iron trench covers had been furnished the general contractor for use in the erection of the building, at a price of $420.00, being for steel and iron trench covers as per specifications; that the same had not been paid, and that a lien was claimed *Page 321
on the lot and buildings to secure payment. The statements in the notice were sworn to by the president of the corporation; and on August 25, 1924, this notice together with the certificate thereto annexed was filed in the County Clerk's office. The Clerk did not spread the notice in full upon the Mechanics Lien Record. An index of the same was made in the trust deed book indexed as follows: "Baptist Church, Charleston, (Name of Trustee or beneficiary) Metal Products Co., (Book Mch) 1, p. 279, (year of record) 1924, (Description or location) Mch. Lien". The Mechanics Lien Record showed the following: "(Name of Parties) Metal Products Co. v. Charleston Baptist Church, (Amt. and character of claim) $420.; (When filed) Aug. 25, 1924, (Description of property) 2 Lots corner of Morris and Quarrier Streets, City of Charleston". The notice itself remained on file, with the notation thereon by the Clerk "admitted to record". It is stipulated by the parties that such was the usual and customary manner of filing and recording such liens adopted by the County Clerk. On what ground the trial chancellor denied the lien, the decree does not state. The exceptions to the Master Commissioner's report are that the notice of the lien was defective; and that it was not recorded as the statute requires. The notice served on the trustees on August 21, 1924, contains all that is required by sub-sec. (e) Sec. 3, chap. 75 Code. It clearly follows the statutory form, and the account of the claim therein contained as having been furnished the contractor for the building is as follows: "June 26, 1924, Trench covers as per specifications $420. Balance due $420." The notice was sufficient. While the notice was not spread in full upon the Mechanics Lien Record by the County Clerk, there was a sufficient recordation as between the petitioner and the owners of the property in order to preserve and perfect the lien. The surety on the contractor's bond agreed to protect the owners against such liens, and if the validity of the lien against the owners is sustained, the Accident Insurance Company as surety on the bond would be responsible. That delivery of the notice to the County Clerk and by him admitted to record, and the *Page 322
substance thereof recorded preserves the lien as between the parties, is decided in Lumber Co. v. Coal Co.,
We now come to the second point relied upon to sustain the decree, namely, that the material was not accepted and was not used in, nor was not necessary to, the completion of the building.
As heretofore stated, appellant says that the trench covers were specially manufactured in length, breadth and thickness, with certain angles, and lugs for lifting, and if not used in the building, were the proper subject of lien, for they could not be used elsewhere. From the substance of the evidence of appellant's witness Moore, and appellee's witness Montgomery (the only witnesses on the point under discussion), it appears that the trench covers were delivered inside the building and the longest ones were actually placed over the trenches (by whom it does not appear) preparatory to pouring of concrete and remained there for some time, but were afterwards, or at least most of them, removed to the lot, and it does not appear what disposition has been *Page 327 made of them. Appellant was not notified of their rejection, and for all it knew they were used in the structure. There appears to have been no objection to the covers, except that they were delivered at the building prematurely, before the work had progressed so that they could be laid. It does not appear that appellant was advised of this rejection. Montgomery says that some one telephoned him that the material was tendered for delivery and asked if it should be accepted, and he refused to accept it. They were properly manufactured according to the specifications and of good quality. The only reason for not putting them in when the work was ready for them, was that a new contractor had been employed to finish the job (the first contractor having failed), the plans were changed, and the new contractor purchased another set of covers. No one says the covers could not have been used by the new contractor. The architect did not ask him to do so.
Our decisions recognize the general rule that there can be no lien under the statute for material furnished the contractor and not used in the structure covered by the contract.Cushwa v. Improvement Co.,
There is conflict in the decisions whether specifically fabricated materials designed for use in a particular building, but not used, can be made the basis of a lien. The weight of authority is to the effect that such material, which cannot be readily used in other structures may be the subject of lien. See Grainger Co. v. Johnson, (286 F. 833), 33 A.L.R. 315, where, in the annotation, the cases are collected.
In 1917, the legislature enacted a statute (chap, 6) whereby the owner could limit his liability where he entered into a contract for the erection of his house, by recording the contract together with a good bond from the contractor, in a *Page 328
penalty equal to the contract price, conditioned for the payment of liens perfected, where the lienors are deprived by the recordation of the contract from receiving from the owner the amount of their liens. The owner who records his contract and bond is exempt from paying more than the contract price, and his property is exempt therefrom, and such liens as are perfected and are not fully paid by the owner, shall be paid by the contractor and his sureties on his bond. In the enforcement of liens where such contract and bond have been recorded, the contractor and his bondsmen must be made parties, and recovery may be had against them without resort to the law courts. The act provides in sec. 14, that if the owner fails to record his contract and bond, or record the contract without bond, or the penalty of the bond is not equal to the contract price, or the bond is not solvent when given, "then the contractor shall be deemed to be the agent of the said owner", and the interest of the owner in the building and land "shall be held liable and subject to such perfected liens, for the full and true value of all work and labor done, and of all materials, machinery and equipment furnished therefor", although the amount may exceed the price stipulated in the building contract. The contract is in the record (not printed), but the bond is not. The bondsman, Accident Insurance Company, intervened and pleaded that it was surety on the contractor's bond and had agreed to save the owners harmless for work and material that might become liens on the property, and asked to be made a party to protect its interest. The presumption is that the bond complied with the statute. The contract appears not to have been recorded. Failure to record the contract accompanied with the bond, makes the contractor the agent of the owner and makes the latter's property liable for all perfected liens for all materialsfurnished therefor. These trench covers, under the statute, were purchased by the owners through Ring-Hartman Company its agents, and were furnished under specifications for the building. We do not think it material to inquire whether these covers were actually incorporated in the building. They were the property *Page 329
of the owners, purchased by them, and they could not refuse to take them solely on the ground of premature delivery, if they had possession at the time the work was ready. Emerson Shoe Co. v. Neely,
The decree will be reversed and the cause remanded to be proceeded with in accordance with the principles herein announced.
Reversed and remanded.
Hummel v. Marshall , 95 W. Va. 42 ( 1923 )
Bailey Lumber Co. v. General Construction Co. , 101 W. Va. 567 ( 1926 )
Prickett v. Frum , 101 W. Va. 217 ( 1926 )
Emerson Shoe Co. v. Neely , 102 W. Va. 158 ( 1926 )
Georgia Lumber Co. v. Harrison Construction Co. , 103 W. Va. 1 ( 1927 )