DocketNumber: 6735
Judges: Maxwell
Filed Date: 2/24/1931
Status: Precedential
Modified Date: 10/19/2024
Defendant complains of a judgment against it, on verdict, for $11,756.25. The action is for damages to an unimproved lot in the city of Fairmont, caused by the erection by defendant's predecessor, Buckhannon Northern Railroad Company, of an overhead bridge or viaduct in front of said property and in the immediate proximity thereof.
The first error assigned pertains to plaintiffs' instruction No. 6, wherein the jury were told that if they found from the evidence that the plaintiffs were entitled to a recovery, then "the plaintiffs are entitled to 6% interest per annum upon the amount of said damages ascertained as aforesaid from the date of such injury to their said real estate to the date of your verdict." The distinguished and able lawyer who presided as special judge in the trial of this case permitted himself to fall into error on this somewhat involved question of interest in its relation to damages. There undoubtedly are situations in which the allowance of interest from date of injury to, or misappropriation or destruction of, property to the date of verdict may properly be included, but not so in a case such as at bar.
*Page 157"Interest is denied when the demand is unliquidated for the reason that the person liable does not know what sum he owes, and therefore cannot be in default for not paying. Gross damages which are wholly at large, depending on no legal standard, and which are referred to the discretion of a jury, can never be made certain except by accord or verdict There can be no default in respect to their payment and they are never enhanced by interest. But demands based upon market values susceptible of easy proof, though unliquidated until the particular subject of the demand has been made definite and certain by agreement or proof, are not so uncertain that no default can be predicated of any delay in making payment. A demand is unliquidated if one partly alone cannot make it certain, — when it cannot be made certain by mere calculation; but the allowance of interest as damages is not dependent on this rigid test." 1 Sutherland on Damages, (4th Ed.), sec. 347.
"As a general rule, interest is not recoverable in tort actions in the absence of a statutory provision to the contrary, for the reason that such damages are ordinarily unliquidated in their character." 8 Ruling Case Law, page 536.
Many cases are in accord. This general rule is to be contrasted with that found in cases where the amount of the injury is definitely ascertainable as of a fixed time. In such instances, interest by way of damages for withholding compensation may be allowed as of right. 17 Corpus Juris, page 826. Such were the situations in our cases ofMcCullough v. Clark,
Counsel for plaintiffs, however, vigorously urge that this court is committed to a different rule because in each of the cases of Fleming v. Railway Co.,
In the case at bar there was no possible basis of calculation afforded to the defendant upon which it could have determined even the approximate amount which it owed the plaintiffs by reason of the injury of which the plaintiffs complain in this action. Such amount remained entirely at large and was dependent for ascertainment upon a jury's finding upon conflicting opinion evidence. There could therefore be no substantial basis nor controlling reason for the allowance of interest prior to the date of the jury's verdict. The question of interest is here very important in view of the fact that the case was not tried for about fourteen years after the erection of the viaduct.
Another point of error goes to the admission of evidence on behalf of the plaintiffs, over the objection of defendant, as to prices paid by defendant for other pieces of property in the immediate vicinity of the plaintiffs' property. The rule as to such evidence was settled in Railroad Co. v. Bonafield,
By the last point of error the right of the plaintiffs to recover at all from the defendant in this action for the alleged wrong is challenged, even if it be conceded that plaintiffs' property has been damaged by the erection of the bridge, because it is said the damage was caused by the defendant's predecessor, the Buckhannon Northern Railroad Company, which built the bridge. On this proposition the defendant relies on our case of Byrne v. Public ServiceCompany,
It is unnecessary to consider other assignments of error relied upon because two of them pertain merely to incidents of the trial not likely to arise on a re-trial; the remaining one goes to alleged excessiveness of the verdict, and is, of course, eliminated by the reversal.
Because of the erroneous prejudicial instruction as to interest, we reverse the judgment, set aside the verdict and remand the case for a new trial.
Reversed; verdict set aside; new trial awarded.