DocketNumber: No. 08CA3213.
Judges: Abele, McFarland, Kline
Filed Date: 6/20/2008
Status: Precedential
Modified Date: 11/12/2024
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 141 {¶ 1} This is an appeal from a Scioto County Common Pleas Court judgment, entered after a trial to the court, for Portco, Inc., plaintiff below and appellee herein, on its claim against Eye Specialists, Inc., defendant below and appellant herein.
{¶ 2} Appellant assigns the following errors for review:
The trial court erred by failing to credit defendant for the entire amount of the West Virginia electric lien.
The trial court erred in failing to award defendant damages pursuant to the contract based upon plaintiff's failure to complete the work prior to the completion date.
The trial court's decision that plaintiff failed to provide credible evidence to support defendant's claim for unworkmanlike performance of a contract is against the manifest weight of the evidence.*Page 142
{¶ 3} In July 2003, the parties entered into a contract whereby Portco agreed to renovate a former NAPA auto body parts store into a medical facility for use by Eye Specialists. In return, Eye Specialists promised to pay Portco $320,178. Because Eye Specialists wanted to open its Portsmouth office as soon as possible, the contract called for "substantial completion" of the building no later than November 27, 2003. The contract defined "substantial completion" to mean possession of an "occupancy permit." If the renovation was not substantially completed by that time, Portco agreed to pay a $200 per day penalty. In the end, Portco did not obtain the required "occupancy permit" until several months after the targeted completion date.
{¶ 4} Portco commenced the instant action on September 28, 2004 and alleged that the contract was completed, but Eye Specialists owed an additional $31,061.13 for extra construction (change orders) that it had requested. Eye Specialists denied liability, counterclaimed for various alleged breaches of the contract, and requested compensatory damages in excess of $25,000.1 Portco denied any liability on the counterclaim.
{¶ 5} At the November bench trial, the parties focused on the change orders and their impact on the overall contract. Gary Cunningham, owner of Portco, testified at length about numerous change orders Eye Specialists requested during construction. John Kendall, a carpenter and inspector, testified that roof leaks in the building were caused by faulty installation of a generator. The witness explained it would take $8,000 to $10,000 to repair the roof. Likewise, Terry Lee Shultz, the clinic director for Eye Specialists, testified that he was quoted $10,000 to repair the roof.2
{¶ 6} The trial court entered judgment for Portco on December 1, 2006. The court concluded that due to the various change orders, Portco was not at fault for the delay in completing the construction project. Further, the court ruled that Portco was due and owing $17,885.13 for additional work that it had performed.
{¶ 7} An appeal was taken from that judgment, but we dismissed it for lack of a final order due to an unresolved counterclaim. See Portco, Inc. v. Eye Specialists,Inc.,
{¶ 9} We believe that appellant fails to distinguish the mechanic's lien and the contractual obligation (or debt) that underlies it. See Schlueter v. Shaheen
(Nov. 8, 1989), Hancock App. No. 5-88-27,
{¶ 10} Here, the trial court's order voiding the mechanic's lien on Eye Specialists' property removed WVE's security in that property for payment of the generator. It did not affect the underlying debt Portco owed WVE for that material.
{¶ 11} Accordingly, we find no merit in appellant's first assignment of error, and it is hereby overruled.
{¶ 13} In its December 1, 2006 judgment, the trial court found that "it would be inappropriate to assess" a penalty for the failure to timely complete the *Page 144
construction because the delay resulted from Eye Specialists' change orders. Generally, an appellate court should not reverse a trial court's factual finding if that finding is supported by some competent, credible evidence. Shemo v. MayfieldHts. (2000),
{¶ 14} Gary Cunningham, the owner of Portco, testified about the numerous change orders that Eye Specialists requested. He also stated that, but for those change orders, the construction would have been completed by the November 27, 2003 deadline. This is sufficient to support the trial court's conclusion on the matter.
{¶ 15} Accordingly, we hereby overrule appellant's second assignment of error.
{¶ 17} As trier of fact, questions of weight and credibility generally rest with the trier of fact. See Colev. Complete Auto Transit, Inc. (1997),
{¶ 18} In the case sub judice, the trial court stated that it did not find the expert's testimony to be credible. Because this appellate court is not in a position to view that witness, or hear his testimony, we should not "second-guess" the trial court on the issues of evidence weight and witness credibility.
{¶ 19} Accordingly, we hereby overrule appellant's third assignment of error.
{¶ 20} Having reviewed all errors assigned and argued by appellant in its brief, and finding merit in none of them, the judgment of the trial court is affirmed.
Judgment affirmed.
McFARLAND, J., concurs.
KLINE, J., concurs in judgment and opinion as to assignments of error II and III, and dissents as to assignment of error I.