DocketNumber: 1235
Citation Numbers: 249 P. 790, 35 Wyo. 381
Judges: Kimball, Potter, Blume
Filed Date: 10/5/1926
Status: Precedential
Modified Date: 10/18/2024
This is an action for the recovery of an amount claimed to be due under a contract for the sale, removal and reconstruction of a drilling rig intended to be used in drilling for oil. The defense was non-performance of the contract. A jury trial resulted in a verdict and judgment for the plaintiff and the defendants appeal.
The defendants, Independent Producers Consolidated and Wyoming Star Oil Company, are corporations engaged in prospecting and developing oil and gas lands. Their managing officer, at the times herein mentioned, was H.A.W. Myrin. The contract was with the Independent Producers Consolidated, and the judgment was against that company. There are no points made on this appeal that require any further reference to the Wyoming Star Oil Company. The First State Bank, another defendant, was made a party because it was the paying agency, as will further appear on a recital of the facts. Hereinafter we shall refer to the Independent Producers Consolidated as the defendant.
In August, 1921, the defendant was looking for a second-hand drilling rig to be used in drilling a well 47 miles north of Moorcroft. The plaintiff, Lusk Lumber Company, had such a rig located near Osage. A Mr. Jackson, who did not testify in the case, inspected this rig for defendant, and thereupon, about September 1, 1921, he and plaintiff's manager prepared a form of contract between the plaintiff and defendant. The material stipulations of the contract were that plaintiff agreed to sell to defendant the drilling rig, described as a "seventy-two ft., twenty ft. base standard rig;" that plaintiff agreed to move and rebuild the rig furnishing certain specified new parts and extra braces, and replacing materials damaged by tearing down and moving; that defendant would pay *Page 386 for the rig when so moved and rebuilt the sum of $4600; that a certified check for said amount be deposited by the defendant with the First State Bank, said check to be mailed to the plaintiff when "contract is completed and passed on" by the defendant.
The writing embodying this contract was sent to Mr. Myrin for his approval and the defendant's signature. The defendant signed upon condition that the rig be completed by October 1; that the "wooden crown blocks can be used for drilling to minimum 2500 feet," and that the certified check for $4600 would be mailed to plaintiff at the date "when contract is completed and passed on by myself (Myrin)." It is admitted that plaintiff agreed to these changes or amendments of the writing. The bank notified the plaintiff that Myrin had deposited with it $4600 to pay to plaintiff according to the terms of the contract. The plaintiff then proceeded to tear down, move and rebuild the rig. On September 22, plaintiff notified Myrin that the rig would be completed and ready for inspection September 25. Myrin replied that he could not make an inspection until the 29th. The inspection was made on the 29th. Mr. Myrin came from Riverton for that purpose accompanied by his attorney and Mr. Hall, a rig builder. Mr. Hall, in the presence of Mr. Myrin and plaintiff's manager, examined the rig, and on September 30 made out a formal, written report in which he set forth 18 specific defects in the rig, stated that there were other minor defects too numerous to mention, and advised against any attempt to repair the structure. This report was sent to the plaintiff with a letter from Mr. Myrin stating that in the face of the report he was unable to accept the rig.
On October 6, plaintiff wrote to Mr. Hall stating in substance that it wished to make the rig satisfactory, but that some of Mr. Hall's objections related to matters not covered by the contract. Mr. Hall was asked to make out for plaintiff a list of materials that would be necessary to *Page 387 put the rig in "A 1 shape," and to state what he would charge to work with plaintiff's workmen while the rig was being made over so plaintiff would know that when completed it would be right. This letter to Mr. Hall was answered October 13 by Mr. Myrin who stated that he was sorry to repeat that he was unable to accept the rig, and that any additional work would be of no benefit to defendant and would not comply with the contract. He gave as his reasons Mr. Hall's report of September 30, in which he advised against an attempt to repair; that Mr. Hall stated that if the rig should be completely rebuilt it would be a patched-up job, and dangerous to workmen; that the rig had not been completed within the time stipulated by the contract, and that it could not be put in shape for drilling by October 25, the time when defendant was obligated to commence drilling.
To this last letter the plaintiff, on October 18, replied by telegram as follows:
"Rig erected per contract and within time fixed. Entitled to and demand payment. Consider objections of Mr. Hall for most part trivial and concerning matters not covered by contract but to be more than fair are willing to meet every substantial objection and have work required for that purpose done by October twenty-fifth. In making this offer we do not admit non-compliance with contract nor that anything further is required. Wire answer."
This telegram was not answered. There were no further communications between the parties, and the plaintiff soon commenced this action.
The defendant claims that the petition is defective in failing to allege performance of the contract, and that the court erred in overruling a demurrer. The allegations of the petition that have reference to performance of the contract are these: *Page 388
"That the plaintiff immediately upon the execution of the contract aforesaid set about in good faith to fully perform said agreement; caused the rig mentioned in the contract above set out to be taken down at its former location twelve miles southwest of the town of Upton, Weston County, Wyoming, and the materials therein contained, together with the new materials required to complete the work, to be transported to the defendants' location as aforesaid, and caused said rig to be rebuilt at said location; that the plaintiff has substantially performed all the conditions on its part to be performed, and on the 22nd day of September, A.D. 1921 notified the defendant Independent Producers Consolidated and H.A.W. Myrin that the moving and re-building of said rig had been completed and that the same was ready for inspection by the defendant; that some days later, to-wit, on the 29th day of September, 1921, the defendant inspected said rig and by a letter dated October 1, 1921, made certain objections thereto of a trivial character and concerning matters not covered by the contract; that thereupon the plaintiff without admitting non-compliance with the contract or that anything further was required, offered to meet every substantial objection made by the defendant, which said offer was declined by the defendant; that said defects may be remedied and said omissions supplied at a cost not to exceed Four Hundred Fifty Dollars ($450.00) which said sum the plaintiff deducts from the balance due on said agreement as aforesaid."
The prayer was for "the sum of $4600 less the sum of $450 required to fully complete the work aforesaid, or a net sum of $4150," with interest, etc.
It is agreed that this is a suit on the contract and not on a quantummeruit or a quantum valebant. The petition should allege performance, or a sufficient excuse for nonperformance, of conditions precedent. In alleging performance, the code permits a general allegation that the *Page 389
party "duly performed all the conditions on his part." Wyo. C.S. 1920, Sec. 5681. If a party does not avail himself of this provision of the code, he should allege specifically the facts to show a performance of the conditions. Korbly v. Loomis,
The plaintiff in the case at bar does not avail itself of the statute. The general allegation of the petition is that plaintiff "substantially" performed. It is evident from other allegations that the word "substantially," was not intended as an equivalent of "duly," and that the pleader did not intend to rely upon full or strict performance. The petition admits that there were defects to be remedied and omissions to be supplied. The plaintiff seeks to bring itself within the rule permitting a recovery in a suit on a contract that has been substantially performed by deducting from the contract price the amount necessary to remedy defects and supply omissions. It is usual in such cases for the pleader to allege performance, and the allegation of performance will permit of a recovery on proof of substantial performance with deductions sufficient to compensate the defendant for defects and omissions. Finley v. Pew,
The plaintiff argues that the defendant waived its right to object to an adverse ruling on the demurrer by subsequently answering and proceeding to trial. The petition, without a sufficient allegation of performance, failed to state a cause of action, and that objection was not waived. Wyo. C.S. 1920, Sec. 5653; 3 C.J. 668.
Error in overruling a demurrer to a petition may in some circumstances be harmless. The answer or reply may supply allegations omitted from the petition. Insurance Co. v. McGookey,
It seems to be conceded that the contract provision that payment should be made when the rig was completed and "passed on" by Myrin, meant that Myrin should approve the work, or that the work should be completed to his satisfaction, before anything became due. This seems to have been the theory of the plaintiff in drawing the petition in which it is alleged that Myrin wrongfully and unreasonably withheld his approval, and much of the evidence introduced by plaintiff was seemingly offered for the purpose of proving this allegation. The defendant claims that the evidence was insufficient to support a finding that Myrin's approval was wrongfully or unreasonably withheld. We think the finding was justified, if the jury believed *Page 392 the plaintiff's evidence. But probably no finding on that point was necessary, as the stated provision of the contract was not mentioned in any instruction given or requested, and no argued assignment of error is based on this omission.
There was a sharp conflict in the evidence on the issue of non-performance. Much of the testimony was given by expert rig-builders, and the questions and answers were often illustrated by reference to a miniature drilling rig. Some of this testimony is not easy to understand from a reading of the transcript. It is not necessary to undertake any detailed recital of the evidence on this issue. It will be sufficient to say that the plaintiff's evidence tended to prove that the rig was completed in compliance with the contract with a few trivial omissions that could have been supplied at an expense of about $10. The defendant's evidence tended to prove that the rig was not erected in a workmanlike manner, and not fit or safe for use for the purpose for which it was intended.
The defendant argues that the doctrine of substantial performance has no application to the contract in question, because it is not a "building" contract, and authorities are cited for the purpose of showing that a drilling rig is not a building or fixture. We do not decide whether the drilling rig became a fixture, or whether the contract was what is commonly called a "building contract." The doctrine of substantial performance is most frequently applied to building contracts, and it is there, perhaps, that the reasons for its application are clearest, but it is not confined to those cases. Page on Cont. (2d ed.) Sec. 2778. The reasons underlying the doctrine make it applicable to all cases where it would be unjust to the plaintiff to declare a forfeiture of his work and materials. Williston on Cont. Sec. 805. In order for the plaintiff to claim compensation for a substantial performance, it must appear that he has tried in good faith to perform. His default *Page 393 must not be wilful. The defendant's right in all cases to have the contract performed is still maintained, at least in theory. When the doctrine of substantial performance is applied, the defendant must receive a fair compensation by deduction from the amount that would have been due for full performance. If the defects are so serious as to deprive the property of its value for the intended use, or if they so pervade the whole work that a deduction in damages will not be fair compensation, the plaintiff cannot rely on substantial performance. Williston, supra, Sec. 805.
In determining whether a forfeiture of plaintiff's work and materials would be unjust, the benefit or lack of benefit to defendant from a part performance is an important element. Williston, supra, Sec. 843. In cases involving contracts for the construction of improvements on lands, the element of benefit to the defendant, the owner of the land, is usually present, and it would often be clearly unfair to permit the defendant, without paying anything, to use and enjoy a structure which is substantially like that for which he contracted. The same principles applicable to building contracts must be applicable to other contracts where there is substantial performance of which the benefit enures to the defendant. Williston, supra, Sec. 842. Whether those principles can be extended to contracts for the manufacture of chattels which have not been accepted by the defendant, seems a doubtful question. Harrild v. School District,
The drilling rig, though it may not have been a building or a fixture, was as unwieldly as many buildings, and *Page 394 could not practically be retained by plaintiff when defendant refused to pay for it. If it was constructed in substantial compliance with the contract, according to the principles above stated, and the defects could have been corrected at slight expense, we think it would be unfair to hold that the plaintiff was not entitled to recover for his work and materials. It must be kept in mind, however, that the structure in question was intended for one purpose only — to drill a well — and if, because of defects for which plaintiff was responsible, the structure had no value for that purpose, the plaintiff's claim had no equity. This brings us to a consideration of instruction No. 7, as follows:
"The Court Instructs the Jury that, if you find that the plaintiff is entitled to recover and if you further find that the defects, if any, complained of by the defendants, are remediable without taking down and reconstructing any substantial portion of the rig, the amount of deduction from the contract price to which the owner is entitled, is the expense of making the work conform to contract requirements. If, on the other hand, you find that the plaintiff is entitled to recover and you further find that the defects, if any, may be remedied only by taking down and doing over some substantial portion of the work involving such expenditure that the contractor would be deprived of adequate compensation, the amount to be allowed to the defendants is the amount which the rig is worth less, by reason of the defect, than it would have been if constructed in entire conformity to the contract."
The instruction should not have been given. It had no application to the facts in the case. If the plaintiff was entitled to recover on the contract the only proper measure of damages was the contract price less the expense of making the work conform to the contract requirements. A statement of this measure of damages is to be found in *Page 395
the first sentence of the instruction, but throughout the instruction the jury is given plainly to understand that the plaintiff may recover though defects in the rig cannot be remedied except by taking down and reconstructing a substantial portion of it. The principle expressed in the instruction is applicable to some cases involving building contracts. Jacob v. Kent,
No well has been drilled at the place where the rig was set, and the evidence shows that the plan to drill has been abandoned. The rig in question has not been used and there is no reason to suppose that it will ever be used for any purpose. It may, perhaps, be inferred, as plaintiff contends, that the plan to drill had been abandoned before September 29, when the rig was inspected by Myrin and Hall, and, therefore, that defendant had a motive for refusing to accept the rig even though it was not defective. It is not contended, however, that the fact that defendant had decided not to drill changed in any way the rights *Page 396 and duties of the parties with respect to performance of the contract. But the jury had before it evidence to show that the rig, even if perfect, would not have been used by defendant, and that, as a practical matter, a defective rig was worth to defendant just as much as a perfect one. In these circumstances, the instruction was particularly dangerous.
Instruction No. 5 was as follows:
"You are instructed that it is the law that, where one contract for the erection of a certain structure, he is entitled to have it erected in conformity with the provisions of his contract; but in the application of this rule the law requires only a substantial compliance therewith. By the use of this term "substantial compliance" you are to understand that it does not require absolute compliance. Slight variations or deviations from the contract as are inadvertent or unintentional and not due to bad faith and which do not impair the structure as a whole, are excusable, and as applied to this case, if the defects complained of by the defendants are only slight and do not impair the structure as a whole and the plaintiff acted in good faith in relation thereto, then defendants cannot complain of said defects."
This instruction probably states a correct principle for consideration in determining whether or not there was substantial performance. But it is not limited to that question. Even slight variations or deviations from the contract which do not impair the structure as a whole, may give the defendant the right to a reduction in damages, and the jury should not be told in such a general way that they are excusable, and defendant cannot complain of them.
On a view of the whole record we are sure that we would not be justified in holding that the error in overruling the demurrer to the petition was harmless. On this *Page 397 point we have considered the instructions, although the plaintiff is probably right in its contention that the trial judge's nunc pro tunc order, the only thing to show exceptions to instructions, is not incorporated in the record. Further, our discussion of what seem to us material defects in the instructions will be of some benefit on a new trial.
Since the trial the assets of the First State Bank have passed into the hands of a receiver. The attorney for the receiver has filed a brief in which he makes several contentions that do not seem to have been made in the trial court. We deem it unnecessary to consider them. When the petition is amended, the receiver no doubt will have an opportunity to appear and make any defense he may have.
The judgment will be reversed, and the case remanded for a new trial with instructions to sustain the demurrer to the petition with leave to amend.
Reversed and Remanded with Instructions.
POTTER, Ch. J., and BLUME, J., concur. *Page 398
Weed v. Idaho Copper Co. , 51 Idaho 737 ( 1932 )
Lusk Lumber Co. v. Independent Producers Consolidated , 46 Wyo. 341 ( 1933 )
Smith v. Gunniss , 115 Mont. 362 ( 1943 )
Interstate Bldg. Corp. v. Hillis , 17 Tenn. App. 171 ( 1933 )
Rosenblum v. Sun Life Assur. Co. of Canada , 51 Wyo. 195 ( 1937 )
Lusk Lumber Co. v. Independent Producers Consol. , 43 Wyo. 191 ( 1931 )
Parkinson v. Roberts , 78 Wyo. 478 ( 1958 )
Sagebrush Development, Inc. v. Moehrke , 604 P.2d 198 ( 1979 )
Buttrey Food Stores Division v. Coulson , 620 P.2d 549 ( 1980 )
Lusk Lumber Co. v. Independent Producers' Consolidated , 36 Wyo. 34 ( 1927 )